Boliden grows global zinc footprint with $1.8 billion Nexa dealNevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plant Boliden grows global zinc footprint with $1.8 billion Nexa dealNevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plant

Tietto Minerals commences wet commissioning at Abujar Gold Project, Côte d’Ivoire

West African gold explorer Tietto Minerals (ASX:TIE) is pleased to announce it has commenced wet commissioning for its 4.5 million tonnes per annum (tpa) carbon-in-leach (CIL) processing system at the Abujar Gold Project in Côte d’Ivoire.

The company says the first gold pour is expected to be completed within 10 days, and the construction of the project is reportedly on budget and schedule.

Tietto Minerals Managing Director Dr Caigen Wang says to build a gold mine the size of Abujar in less than 12 months is a monumental achievement.

“To do it during COVID with supply chain issues, escalated pricing and skilled people shortage made it, almost, mission impossible. Our in-house construction team has demonstrated it can be delivered through careful planning, diligent management and hard work.

“Our in-house construction team has demonstrated it can be delivered through careful planning, diligent management and hard work”

What a great team achievement led by the captain, our Chief Operating Officer Matthew Wilcox. I would like to thank our mine construction team, ESG team, mining team, contractors, and consultants, local communities, government authorities at various levels and many more.

We would also like to thank our shareholders who have put us into a position where we have no debt, zero hedging and are in a position to produce around 260,000 ounces in the first 12 months of production once we reach commercial production.”

Tietto Minerals Chief Operating Officer (COO) Matthew Wilcox says he is extremely proud of the team who have delivered the project in less than 11 months from pouring first concrete.

I believe this is the most challenging schedule for a project of this magnitude that has been achieved in the last decade in the last decade in West Africa. A schedule made possible by an outstanding owners’ team and a great team of contractors and consultants who achieved the job safely and on budget.

I would like to thank the construction team led by Daniel Kotzee, our outstanding engineering consultants in Primero and ECG, as well as our key contractors Wacom, Friedlander, NCP, EPSA, Peloton, and Emikon, as well as many other local contractors who all went above and beyond to achieve the schedule.

A great effort by the project’s commercial team, led by Hesbon Okwayo, who achieved an outstanding result under difficult global conditions, and supported by Antrak logistics and Bollore, who managed to get the equipment to site in the time frames required.”

Tietto forecasts Abujar will produce 260,000 ounces of gold in its first year of production, with the first gold pour expected within the next 10 days. 

The company also states it is ‘uniquely’ positioned to advance its dual strategy of ‘Drill and Build’ which consists of driving resource growth at the project and increasing the gold production profile.

In addition to the gold production, Tietto aims to complete up to 120,000m of diamond drilling this year with a fleet of 8 rigs in operation and on track to deliver a resource update this quarter.

Tietto Minerals is a West African gold exploration company focused on developing the Abujar Gold Project in Côte d’Ivoire. Currently Abujar has a mine life of 11 years, with scope for the company to extend this with further near-mine and regional exploration success.

Images: Tietto Minerals Ltd