PC Gold (ASX:PC2) has completed a Prefeasibility Study (PFS) for its Spring Hill Gold Project in the Northern Territory, outlining a maiden ore reserve.
The PFS outlines a standalone operation comprising open-pit and underground mining, feeding a new gravity and carbon-in-leach processing plant with a capacity of 4 million tonnes per annum.
At a gold price of $5,500 an ounce, the study returns a pre-tax net present value (NPV) of $1,591 million at a 5% discount rate and an internal rate of return (IRR) of 66%. Post-tax figures indicate an NPV of $1,239 million and a 56% IRR.
Forecast production totals 1.03 million ounces (Moz) of gold over 9.5 years, with average annual output of about 120,000 ounces during the first five full years.
The study also projects an all-in sustaining cost of $2,870 per ounce, pre-production capital expenditure of $413 million, and a pre-tax payback period of 1.3 years from first gold, which is targeted for Q1 2029.
Maiden reserve estimated
The Spring Hill PFS outlines a maiden probable ore reserve of 35.5 million tonnes (Mt) at 0.83 grams per tonne gold (Au) for 951,000 ounces. This comprises 901,000 ounces from open-pit material and 50,000 ounces at 3.14g/t Au from underground material.
Estimated at $4,500 per ounce, the reserve returns a pre-tax NPV of $739 million and an IRR of 39%.
The reserve represents 77% of the indicated ounces in the July 2026 interim mineral resource estimate (MRE) of 75.9Mt at 0.80g/t Au for 1.92Moz, with all inferred material treated as waste.
Inferred material accounts for about 12% of the production target by contained ounces, and about 65% of the underground inventory.
Executive Chairman Ashley Pattison says the company sees room to expand.
“With four rigs operating, around 40,000m already drilled beyond the resource cut-off, and underground drilling to commence in early 2027, we see clear scope to grow both the resource and the reserve ahead of the DFS,” Pattison says.
An MRE update is targeted for March 2027, with 20,000m of phase-one underground drilling and environmental referrals scheduled for Q1 2027.
PC Gold is also targeting a Definitive Feasibility Study (DFS) and final investment decision (FID) in Q3 2027.
The company holds about $85.5 million in cash, which it says is sufficient to reach a FID. However, funding arrangements are not yet in place for the $413 million development.
PC Gold is an Australian gold explorer and developer focused on its flagship Spring Hill Project in the Pine Creek region of the Northern Territory, about 200km southeast of Darwin.
Write to Paula Fabe at Mining.com.au