PC Gold (ASX:PC2) plans to start drilling at Steve’s Gully within three weeks, following a targeting review that defined 37 prospects at its Spring Hill Gold Project in the Northern Territory.
The review compiled 175 historical exploration reports, including 3,600 digitised pages, across the consolidated 10,300-hectare land package. It marks the first project-wide targeting of 40 years of data.
The 37 targets sit outside the current interim mineral resource estimate (MRE) of 43.6 million tonnes @ 1.1 grams per tonne gold (Au) for 1.5 million ounces, at a 0.5g/t Au cut-off.
A total of 16 are drill-ready, including nine tier-one priorities with historical results that were never followed up.
At Steve’s Gully, Ross Mining returned 16m @ 4.12g/t Au from 63m in 1994, with no work since. Acacia Resources intersected 5m at 24.4g/t Au from 7m at First Bite in 1995–96 but tested only about 60m vertically over 265m of strike.
Further north, 11 of 16 channels along an 800m gossanous reef at Gentry’s Chance returned at least 1.46g/t Au, with a maximum of 7.49g/t Au.
The review also identified ‘high-grade’ historical channel samples not previously incorporated into the MRE, including 5m @ 9.4g/t Au at Hong Kong and 5m @ 27.2g/t Au at Middle Zone. This data will be assessed for a December 2026 MRE update.
Outside the resource, Macau Extended returned 10m @ 17.5g/t Au, which will feed into the current reverse circulation program.
A total of 15 never-sampled areas were also identified, including a 4km belt along the McKinlay Granite contact in the recently acquired Terracore Gold tenement package.
Drilling schedule and critical path
Drilling will begin at Steve’s Gully, followed by Vein Heaven early next year and the Macau Extended infill program. Tier-two and tier-three targets will undergo mapping, rock-chip, and soil sampling first.
Executive Chairman Ashley Pattison says Spring Hill has been explored by a dozen companies over 40 years but never as a single consolidated package.
“This regional pipeline now gives us a ranked list of drill and field programs that can run alongside the resource drilling for several years,” Pattison notes.
Pattison adds that Prefeasibility Study workstreams and permitting remain the critical path, with exploration running in parallel.
The historical results come from reports lodged with the NT Geological Survey and have not been independently verified by the company.
PC Gold is an Australian gold exploration and development company advancing its flagship Spring Hill Gold Project in the NT.