Agnico Eagle Mines (TSX:AEM) has outlined plans for approximately 10,000 hires over 2025–2030 to support mine construction and expansion, with about 3,500 already completed.
The company’s 18 November capital markets day presentation shows it had achieved 35% of the hiring target by 30 September, leaving approximately 6,500 hires remaining.
Recruitment initiatives include an expanded graduate program, Indigenous career opportunities, skilled-worker immigration, and training through its Macassa mining school in Ontario, Canada.
Agnico is also staggering project development so construction teams, equipment, and expertise can move between sites as work progresses. Its in-house construction group comprises approximately 400 people.
Executive VP and COO Natasha Vaz says the hiring target covers growth, retirements, and employee turnover.
Projects underpin production ambitions
Agnico says it is targeting annual gold production growth of 20–30% over the next decade, with potential to exceed 4 million ounces in the early 2030s.
The pipeline centres on Canadian Malartic in Québec, Detour Lake and Upper Beaver in Ontario, and Hope Bay in Nunavut.
At Canadian Malartic, underground production through Odyssey’s first shaft is expected to begin ramping up in June 2027. The first shaft and ramp could support approximately 550,000 ounces annually by 2029.
Hope Bay is expected to produce 400,000–435,000 ounces annually, with first gold targeted for the first half of 2030.
Some expansion plans remain preliminary. Agnico says evaluations for several projects include inferred mineral resources, while further development at Detour Lake underground and Upper Beaver remains subject to permits and board approval.
Write to France Pinzon at Mining.com.au