Vale (NYSE:VALE) has received court approval to partially resume operations at its Viga iron ore mine in Congonhas, Minas Gerais, Brazil, nearly 10 months after suspending work at the site.
The Minas Gerais court authorised the restart with the consent of federal prosecutors after Brazil’s National Mining Agency and the state environmental authority gave their approval. Vale’s 23 November filing did not give a restart date or specify which activities would resume.
Vale says the planned Viga restart leaves its 2026 iron ore production guidance unchanged at 335–345 million tonnes (Mt). In its third-quarter results, the company said it expected production at the lower end of that range.
Vale halted operations at Viga and the nearby Fábrica mine in Ouro Preto after sediment-laden water overflowed at both sites on 25 January. In February, the company said it had begun cleaning and dredging affected waterways and was monitoring nearby streams daily.
The shutdowns were the main reason iron ore production across Vale’s Southern System fell by 1Mt from a year earlier to 12.1Mt in the June quarter, according to the company’s production report.
Fábrica partially reopened in September under an agreement Vale reached with the state government and state prosecutors in August. The agreement set out a schedule for resuming operations and called for environmental remediation, structural safety measures, and an independent audit. The court authorised Fábrica’s partial restart after reviewing additional technical information from Vale.