MDF Global MDF Global
Finland’s nuclear waste repository puts Australia in focus•Junior explorers on road to unlocking Africa’s mineral wealth•A royal-blue legacy older than the pyramids: Lapis lazuli•Western Australia’s gold pipeline keeps growing•Sahel gold miners step up security amid jihadist threats•Lake Vermont’s $1.3 billion coal extension to support 860 jobs•Codelco reports $2.11 billion nine-month loss after asset write-downs•Copper price sweeps higher as China offers stock market support•Codelco leadership shake-up continues as commercial chief departs for Trafigura•Gold price climbs 3% as tech stocks rebound•Kazakh banks raise $2.26 billion to fund private takeover of gold miner•Australia and Mozambique discuss mining investment•Liberia signs $8.6 billion Bea Mountain infrastructure deal•China Shenhua raises $1.29 billion in Hong Kong share sale•Ivanhoe Mines backs AI for Angola copper exploration•Rio Tinto JV ships first Simandou iron ore to Europe•Genesis Minerals completes Vault gold takeover•1911 Gold raises ceiling on $14.8 million private placement•Copper Road paves way to Ben Nevis drilling•BlueScope opens Western Sydney coating line Finland’s nuclear waste repository puts Australia in focus•Junior explorers on road to unlocking Africa’s mineral wealth•A royal-blue legacy older than the pyramids: Lapis lazuli•Western Australia’s gold pipeline keeps growing•Sahel gold miners step up security amid jihadist threats•Lake Vermont’s $1.3 billion coal extension to support 860 jobs•Codelco reports $2.11 billion nine-month loss after asset write-downs•Copper price sweeps higher as China offers stock market support•Codelco leadership shake-up continues as commercial chief departs for Trafigura•Gold price climbs 3% as tech stocks rebound•Kazakh banks raise $2.26 billion to fund private takeover of gold miner•Australia and Mozambique discuss mining investment•Liberia signs $8.6 billion Bea Mountain infrastructure deal•China Shenhua raises $1.29 billion in Hong Kong share sale•Ivanhoe Mines backs AI for Angola copper exploration•Rio Tinto JV ships first Simandou iron ore to Europe•Genesis Minerals completes Vault gold takeover•1911 Gold raises ceiling on $14.8 million private placement•Copper Road paves way to Ben Nevis drilling•BlueScope opens Western Sydney coating line

Silver Mines takes step forward towards Bowdens approval

Silver Mines (ASX:SVL) has cleared another regulatory hurdle at its Bowdens Silver Project in New South Wales, which is considered to be Australia’s largest undeveloped silver deposit.

The NSW Government Department of Planning, Housing and Infrastructure (DPHI) has completed its assessment of additional information submitted by the company and provided supplementary advice to the Independent Planning Commission (IPC).

In July, Silver Mines supplied additional information to support a DPHI assessment of the potential impacts of a proposed transmission line, as well as changes to relevant legislation and policies since Bowdens’ development consent was granted in April 2023. 

The IPC will now consider the supplementary advice as part of its determination process, with a decision expected by 9 December 2026.

Significantly, the DPHI’s assessment does not fundamentally change its previous conclusions about the merits of the project. Its original referral to the IPC found Bowdens to be in the public interest and approvable, subject to strict conditions of consent.

Development work continues

The regulatory progress follows the release of an updated Definitive Feasibility Study (DFS) and the start of front-end engineering and design (FEED) work at the central NSW project.

The updated DFS represents a substantial improvement on the December 2024 optimisation study, with an increase in ore reserves by 30% to 93.5 million ounces of contained silver. Reserve tonnage rose 46% to 47.9 million tonnes.

The DFS also outlines a pre-tax net present value (NPV) of more than $1 billion, a pre-tax internal rate of return (IRR) of 31.5%, and estimated operating margins of $2.39 billion, with a payback period of around three years.

Silver is expected to account for about 91% of future project revenue, aligning Bowdens with the NSW Government’s Critical Minerals and High-Tech Metals Strategy 2024-35.

Fitzgibbon joins board

As it eyes development, Silver Mines has appointed senior mining executive Nicole Brook and former federal resources minister Joel Fitzgibbon as non-executive directors from 17 September. Fitzgibbon is then set to become independent non-executive chair after the company’s annual general meeting in November.

How approval was set back

Bowdens’ 2023 approval was challenged by an activist group, and the NSW Court of Appeal upheld the appeal in 2024.

The dispute centred on the IPC’s administrative process in relation to a potential transmission line to the project.

The transmission line was intended to provide power to the mine, but approval for such enabling infrastructure is traditionally sought through a separate planning application.

The court’s decision resulted in the original development consent being voided on a technical issue under NSW planning regulations.

Since then, the NSW Parliament has passed legislative changes intended to clarify the approvals process for projects such as Bowdens that require transmission lines and other enabling infrastructure.

Silver Mines Managing Director Jo Battershill says: 

“The DPHI’s supplementary advice to the IPC is a significant milestone for the Bowdens Silver Project and Silver Mines shareholders, more than two years since the Bowdens Development Consent was voided on a minor technical issue under NSW planning regulations.”

Battershill says the latest step forward is supported by extensive technical and environmental assessments, as well as continued consultation with the community, stakeholders, and NSW Government agencies.

“The Bowdens team has delivered a robust, environmentally responsible project that supports the NSW Critical Minerals and High-Tech Metals Strategy and offers substantial long-term economic and social benefits for communities across Lue, Rylstone, Kandos, and the broader Mid-Western Region,” Battershill says.

“During the construction phase, Bowdens will employ over 300 direct full-time employees and more than 200 over the planned extensive mine life.”

Silver Mines is focused on acquiring, exploring, and developing silver assets.

Write to Christina Wagstaff at Mining.com.au 

Main image: Silver Mines
Add to Watch List:
Author Image
Written By Christina Wagstaff
Christina is a journalist and communications professional with more than 20 years’ experience across Australia’s leading media, business and finance publications, as well as corporate affairs. She has covered business, markets and resources, particularly precious metals and critical minerals. Outside of work, Christina enjoys running, getting stuck into a good book and driving her kids crazy by being a self-confessed news junkie.