Santos (ASX:STO) has made a final investment decision to proceed with its $400 million Agogo Gas Production Facility Tie-In Project in Papua New Guinea.
The project involves delivering gas from the facility through a new 19km pipeline to the PNG LNG pipeline. This will require two new wells and associated production facility modifications.
The project aims to support Santos’s long-term production profile with a 12-year production plateau.
First gas is targeted in the second quarter of 2028, with potential to continue production beyond 2050.
CEO and Managing Director Kevin Gallagher says that this project will “convert Santos’s 66 million barrels of oil equivalent in proven plus probable undeveloped reserves into developed reserves, delivering incremental net production of around 54 million standard cubic feet per day with significant upside potential depending on reservoir performance”.
“With an expected internal rate of return of greater than 50% and a payback period less than four years from final investment decision, and approximately two years from first gas, the project is expected to be strongly value accretive, support our long-term production profile, and sustain feed gas supply to PNG LNG.”
According to Santos Australia and PNG Chief Operating Officer Brett Darley, key regulatory approvals are in place, land access has been secured, and all material joint venture approvals have been obtained.
“Our focus is now on progressing detailed design for the facility modification, awarding the two main construction contracts, and progressing the temporary construction camp to drive towards first gas in the second quarter of 2028,” Darley says.
Santos holds a 39.9% interest in the PNG LNG joint venture. Other joint venture partners include ExxonMobil PNG (NYSE:XOM), ENEOS Xplora, Kumul Petroleum, and the Mineral Resources Development Company.
Santos is a multinational energy producer with assets across Australia, Papua New Guinea, Timor-Leste, and the US.
Write to Richard Szabo at Mining.com.au