The Queensland Government agreed to remove an Indigenous heritage protection zone for a mining company with ties to a former Liberal National Party of Queensland (LNP) operative.
The Traditional Owners of the land covered by the heritage protection zone in Cape York, Queensland, alleged they were denied an opportunity to be heard in proceedings relating to mining operations conducted by Broken Hill Gold (ASX:BH6).
The Queensland Supreme Court has since overturned the Land Court’s orders that removed the protection zone.
Queensland’s environment department had rejected the mining company’s applications twice before agreeing to scrap the exclusion zone and siding with the company.
However, the Supreme Court found that the Olkola People’s native title trustee, the Ut-Alkar Aboriginal Corporation, had been denied procedural fairness.
The matter has now been returned to the Land Court for reconsideration.
Background to the dispute
The protection zone currently prohibits mining activity within 100m of significant cultural sites at the Alice River Gold Project.
Along with the St George Gold-Antimony Project, Alice River is now owned by Manda Resources — a company backed by Emerald Resources (ASX:EMR).
Broken Hill Gold, formerly known as Pacgold, spun out the North Queensland assets to Manda during a demerger in June 2026, as reported by Mining.com.au.
Following the environment department’s U-turn, the ABC reported that the mining company’s sustainability manager was a former Queensland Young Liberals president.

Shane Goodwin was a campaign manager for a successful 2024 Queensland LNP candidate and an adviser to former federal Liberal MP Andrew Laming.
Goodwin has maintained close associations with the LNP and the Liberal Party, although he has stated that he has no current roles with either party.
The mining company told the ABC that Goodwin’s “other activities” were unrelated to the applications to remove the exclusion zone.
Goodwin was involved in drawing up the original environmental authority applications and personally spoke to the environment minister’s office about seeking amendments to the authorities.
The department initially refused those applications.
Goodwin met with Environment Minister Andrew Powell when the mining company made an application to remove the protection zone in March 2025.
Goodwin described the meeting as being “with representatives across the resources sector”, and said the mining company’s amendment applications were not discussed at the time.
Both applications were rejected by the environment department following opposition from the Ut-Alkar Aboriginal Corporation.
The mining company launched an appeal in the Land Court in late 2025, which was due to be heard in May 2026.
The department made joint submissions with the mining company to the Land Court in March 2026, around eight weeks before the scheduled hearing, seeking to lift the exclusion zone requirements.
The Land Court upheld the mining company’s appeal and scrapped the protection zone.
Supreme Court steps in
The Ut-Alkar Aboriginal Corporation sought a judicial review of the Land Court’s decision in May 2026, arguing that it had been excluded from proceedings and denied natural justice.
In its ruling in late October, the Supreme Court found that the corporation had been denied a reasonable opportunity to be heard.
The Supreme Court’s ruling does not determine whether the exclusion zone should ultimately be removed, but returns the matter to the Land Court for reconsideration.
Mining.com.au is not suggesting that either Goodwin or the minister has acted inappropriately.