Australia’s High Court has dismissed an appeal by MACH Energy, halting a planned extension of the Mount Pleasant open-cut coal mine in New South Wales.
MACH Energy had sought permission to extend the life of the open-cut mine by more than 20 years to 2048. The company argued that coal shipped and burned overseas could not be clearly linked to environmental impacts felt in the Hunter Valley, north of Sydney.
However, in a brief written judgement, the High Court dismissed MACH Energy’s appeal. The High Court found the state’s planning commission failed to consider imposing conditions on the mine that would limit emissions “to the greatest extent practicable”.
The decision stands as a binding national precedent, requiring planning authorities across Australia to account for the local impacts of planet-heating emissions when considering fossil fuel project approvals.
Lead lawyer Anita O’Hart said the implications extend “well beyond Mount Pleasant”.
“This ruling will be applied by courts and planning authorities across Australia, and it will be studied internationally as one of the most significant domestic climate law decisions in the world,” O’Hart remarked.
MACH Energy has reportedly accepted the decision and noted in a statement that it will “continue to actively pursue all available options to ensure the long-term continuity of the Mount Pleasant operation.”
The Minerals Council of Australia has spoken out on the dismissed appeal, with CEO Tanya Constable describing today’s decision by the High Court as “a further blow to Australia’s prospects of meeting continued demand for our high-quality coal from global customers.”
“Developing a coal mine in Australia is already difficult enough because of long approval times, lawfare by activists, and high royalties and other taxes,” Constable pointed out in a separate statement, noting that mines will now have to evaluate how to reduce emissions from their export customers, or scope 3 emissions.
“Now mines may have to work out how to reduce emissions from their export customers, or scope 3 emissions.
“This decision sends a very negative signal to Australia’s trade and investment partners about sovereign risk in this market.
“Australian resource companies should not be forced into a situation where well-funded legal attacks over a number of years require a High Court appeal.
“These legal challenges seek to game the legal system by creating uncertainty and delay without ever having to pay costs.”
Constable added that other investors in the Australian resource sector will ‘carefully’ review the outcome from today’s High Court judgment and its potential ramifications for other projects.
MACH Energy is focused on the acquisition, development, and operation of coal assets, including the Mount Pleasant open-cut coal operation.
Write to Paula Fabe at Mining.com.au
Main image: MACH Energy