Zeus secures 51% of Diaguili Copper-Gold Project ahead of drilling•Zeotech signs AusPozzTM MoU with Sunstate Cement•Golden Horse gallops into Southern Cross drilling•Mt Malcolm expands Golden Crown gold footprint•Hi-View gains full control of Toodoggone•Buxton readies maiden Arizona porphyry drilling•Nickel Industries JV lands $349 million loan•Lake Victoria Gold lines up $33 million financing for Tanzania assets•Narryer appoints Hildebrand to board to advance portfolio•Bulk sample from Iltani’s Orient yields positive results•Giants and junior miners rally as ASX falls•Evergold acquires historical Rabbit Warren gold discovery•Entree lines up Tether affiliate for $40 million placement•Orpheus finds percent-grade uranium at McArthur Project•Lithium Africa fields major funding offers for Springbok•Locksley moves Greater Tottenham into execution phase•PC Gold stacks thick gold intercepts at Spring Hill•Mount Ridley recovers 95% gallium from Darling Range bauxite•Venari joins US Defense Industrial Base Consortium•Orbit pursues opportunities to expand Lewis Ponds Zeus secures 51% of Diaguili Copper-Gold Project ahead of drilling•Zeotech signs AusPozzTM MoU with Sunstate Cement•Golden Horse gallops into Southern Cross drilling•Mt Malcolm expands Golden Crown gold footprint•Hi-View gains full control of Toodoggone•Buxton readies maiden Arizona porphyry drilling•Nickel Industries JV lands $349 million loan•Lake Victoria Gold lines up $33 million financing for Tanzania assets•Narryer appoints Hildebrand to board to advance portfolio•Bulk sample from Iltani’s Orient yields positive results•Giants and junior miners rally as ASX falls•Evergold acquires historical Rabbit Warren gold discovery•Entree lines up Tether affiliate for $40 million placement•Orpheus finds percent-grade uranium at McArthur Project•Lithium Africa fields major funding offers for Springbok•Locksley moves Greater Tottenham into execution phase•PC Gold stacks thick gold intercepts at Spring Hill•Mount Ridley recovers 95% gallium from Darling Range bauxite•Venari joins US Defense Industrial Base Consortium•Orbit pursues opportunities to expand Lewis Ponds
playa verde

Halo Minerals derisks Playa Verde through tribunal decision

The First Environmental Tribunal of Chile has rejected the judicial challenge filed against the Chilean Committee of Ministers’ environmental approval of Halo Minerals’ (AIM:HALO) Playa Verde Project.

The judgement dismissed all claims advanced by the claimant and upheld the October 2025 decision granting a favourable environmental qualification for Playa Verde.

On 28 November 2025, Manuel Cortés Alfaro began proceedings before the First Environmental Tribunal challenging the approval. The matter was heard in April 2026, and the tribunal has now delivered its ruling. The decision focused primarily on allegations concerning potential public health impacts arising from historical tailings material and return sands associated with the development project.

Halo Minerals says the tribunal confirmed that the health risk assessment did not constitute a substantial modification requiring a new public consultation process, and the company’s voluntary environmental commitment to reduce arsenic concentration was legally valid and environmentally appropriate.

Halo Minerals workers

What this means for Halo

The company believes the judgment represents a milestone, derisking the development of Playa Verde and providing judicial validation of the environmental approval process undertaken over numerous years.

Playa Verde is intended to recover copper from historical tailings deposited on Playa Grande while reducing arsenic concentrations in the material returned to the beach. The aim is to return the area to the community in a cleaner condition so it can again be used for recreation and, over time, fishing after decades of historical tailings deposition.

CEO Andrew Dennan says the judgement recognised that Playa Verde will improve environmental conditions within the project area.

“We look forward to progressing the development of Playa Verde,” Dennan says.

The company continues to make progress across various key technical and permitting workstreams at Playa Verde. In conjunction with BIOS Mining & Infrastructure, Halo is advancing the optimisation program and refinement of project economics, with a focus on updating capital and operational expenditures estimates to Bankable Feasibility Study (BFS)-standard.

Updated BFS-level project economics are expected to be completed in the coming weeks. A final investment decision is also targeted for completion by the end of 2026.

Halo is also engaging with potential industrial capital partners in relation to project funding and expects those discussions to continue during H2 2026.

Playa Verde’s initial mineable resources and reserves total 34.2 million tonnes to produce 60,329 tonnes of refined copper. The mine plan is based on dredging and processing 5 million tonnes annually, with an overall metallurgical recovery of 72%.

Halo Minerals is focused on producing key strategic and battery metals through the reprocessing of low-risk, metal-rich, surface-accumulated legacy mining waste projects, with a particular focus on copper.

Write to Aaliyah Rogan at Mining.com.au

Images: Halo Minerals 
Add to Watch List:
Author Image
Written By Aaliyah Rogan
Originally from New Zealand, Aaliyah brings several years of experience covering the resources sector, with a focus on companies, commodities and global mining markets. Her reporting has spanned European markets and the evolving global mining landscape, with a focus on the stories and market forces driving change across the sector.