Black Rock Mining (ASX:BKT) is progressing its early works program at the Mahenge Graphite Project as it looks to commence construction following funding and a final investment decision (FID).
The company has successfully completed community compensation payments for the lower access road, representing the final project area requiring community compensation.
The bulk earthworks contract was awarded to Tanzanian contractor Taifa Mining and Civils in February following a competitive tender process.
Final activities include relocating graves located in the road corridor and constructing the Mdindo stream diversion channel to create unrestricted access to the plant site ahead of the main works program.
The site received more than 500 millimetres of rain in March, creating difficult conditions for earthworks.
Managing Director John de Vries says completion of early works is critical to ensure Mahenge is construction ready:
“Good progress has been made on delivering the early works program since our October ground breaking ceremony. Completion of early works is critical for ensuring that Mahenge is construction ready once we secure full funding and make FID.
“A major highlight is the successful completion of community compensation for the lower access road. This represents a significant milestone for Black Rock which honours our commitment to our project–affected communities and supports continued site access.”
The company has completed preliminary work on the Ifakara to Mahenge 220kV transmission line, including a corridor survey and tower spotting with representatives from the government-owned Tanzania Electric Supply Company and a local biodiversity specialist.
The new power line will connect Mahenge to competitively priced, high-voltage, hydro-dominated power.
“Also pleasing is the completion of preliminary work on the transmission line which will secure access to clean, hydro-dominated power for Mahenge and the region. Access to competitively priced grid power will significantly increase the cost differentiation of Mahenge relative to peers using conventional diesel–generated power,” de Vries says.
Black Rock holds an 84% interest in Mahenge, which has a resource of more than 200 million tonnes and the second-largest graphite reserve globally.
The project should contribute more than 400 full-time-equivalent jobs for module one, rising to above 900 when all four modules are operational.
Black Rock Mining is an Australian company focused on the Mahenge Graphite Project in Tanzania.
Write to Amy Rotman at Mining.com.au
Images: Black Rock Mining