Aguia Resources (ASX:AGR) has conducted the first gold and silver pour through the existing plant as part of the Santa Barbara Project recommissioning in Colombia.
The company began underground mining in early December with processing of the development material starting thereafter.
Aguia, which has a market capitalisation of $39.5 million, is continuing work on upgrading the project. This work includes underground development, processing, and general facilities which will enable Santa Barbara to operate at an expanding processing rate of 50 tonnes per day.
Executive Chairman Warwick Grigor says since taking over Andean Mining six months ago, the company has prepared for, and recommissioned the 30-tonne-per-day pilot plant, as well as achieved the first gold pour.
“Achieving this milestone on capital expenditure of less than $2 million so far should be very pleasing,” Grigor says.
“We are part way through the process of expanding the capacity to 50 tonnes per day, enabling a ramp up of gold production over the next three months, from both development mineralisation and production stopes.
“Importantly, we expect to commence drilling of the extensions of the vein system in the current quarter as the first step in preparation of resource estimates, which are conditions precedent to announcing production guidance.”
Aguia is finalising arrangements with Australian refineries to process Santa Barbara gold and silver doré.
Aguia Resources is a multi-commodity company with pre-production phosphate projects in Brazil and a gold project in Colombia.