Aguia Resources (ASX:AGR) is preparing for the first carbon strip and a subsequent gold pour within the Santa Barbara Gold Project in Colombia, while underground development work progresses.
The commissioning of the first mine stope is expected to be completed by the end of this month.
In conjunction, Aguia, which has a market capitalisation of $44.95 million, is completing and commissioning an additional three agitator tanks to enable processing of a minimum 30 tonnes per day (tpd).
A further four agitator tanks, each of five-tonne capacity, will be installed in the coming months to increase production to the 50tpd target.
Aguia says that a new Merrill Crowe precipitation system has been fabricated and delivered to site. The installation and commissioning of the Merrill Crowe and new gold room will take place this month.

Executive Chairman Warwick Grigor says after a period of recommissioning and overcoming minor mechanical issues, the focus at Santa Barbara is now on showing the benefits of having a “high-grade” gold project.
“Installation of additional capital items will both improve the reliability of the processing plant and enable capacity expansion over the next few months,” Grigor says.
“The commencement of exploration drilling in the current quarter will also enable us to start to appreciate the true dimensions of this unusually high-grade gold system.
“Ongoing project development and exploration activities will see delivering a steady stream of updates over the coming weeks.”
This news comes after Aguia’s wholly owned subsidiary Minera La Fortuna received all necessary approvals for a concession contract to operate the underground workings and processing facility in Santa Barbara.
In early December, underground mining began with processing of the exploration development material starting thereafter.
Aguia has begun underground development work on the Mariana and Santa Barbara vein systems after substantive rehabilitation works.
A total of 25 tonnes of mineralised exploration development material has been mined and delivered to the pilot processing plant, while 246 tonnes of waste material from underground development has been extracted from underground development.
The Santa Barbara Gold Project, comprising 320 hectares, lies in the core of a prolific gold camp on the northern tip of the Serranía de San Lucas belt in Colombia.
Aguia Resources is a multi-commodity company with pre-production phosphate projects in Brazil and a gold project in Colombia.
Write to Aaliyah Rogan at Mining.com.au
Images: Aguia Resources