Lithium’s tale of two markets: What’s driving volatility•Topaz as November’s gift from the Sun God: A Taste of Birthstones•Côte d’Ivoire: The sleeping giant of West African mining•Nornickel linked to Rostelecom underground data centre plan•Alcoa advances up to $8 billion South32 aluminium deal•Congo says China’s Huayou unit must pay compensation despite halt•BHP and Rio shares face test as copper prices stumble•Brazil names 27 critical minerals amid domestic processing push•Purecore sharpens uranium-copper hunt with geophysicist•Column: Tin price hit by AI stock rout despite physical market tightness•Congo says US minerals deals should be judged by projects•MP Materials rare earth operations ‘no longer reliant’ on China•SAGA joins Canada’s business advocacy network, minerals council•Gold price slips following strong US nonfarm payroll print•Nutrien to close White Springs after earnings miss•Hindustan Zinc signs 11 Rajasthan park MoUs•Kazakhstan plans uranium reserve, signs Asian contracts•Indonesia eases FX retention rules for more miners•Physical gold demand rises in India ahead of Diwali•Graycliff five-for-five on Shakespeare gold drilling Lithium’s tale of two markets: What’s driving volatility•Topaz as November’s gift from the Sun God: A Taste of Birthstones•Côte d’Ivoire: The sleeping giant of West African mining•Nornickel linked to Rostelecom underground data centre plan•Alcoa advances up to $8 billion South32 aluminium deal•Congo says China’s Huayou unit must pay compensation despite halt•BHP and Rio shares face test as copper prices stumble•Brazil names 27 critical minerals amid domestic processing push•Purecore sharpens uranium-copper hunt with geophysicist•Column: Tin price hit by AI stock rout despite physical market tightness•Congo says US minerals deals should be judged by projects•MP Materials rare earth operations ‘no longer reliant’ on China•SAGA joins Canada’s business advocacy network, minerals council•Gold price slips following strong US nonfarm payroll print•Nutrien to close White Springs after earnings miss•Hindustan Zinc signs 11 Rajasthan park MoUs•Kazakhstan plans uranium reserve, signs Asian contracts•Indonesia eases FX retention rules for more miners•Physical gold demand rises in India ahead of Diwali•Graycliff five-for-five on Shakespeare gold drilling
Goldfields in Western Australia

Brightstar advances Goldfields towards first gold

Brightstar Resources (ASX:BTR) says construction of its Goldfields Project in Western Australia remains on schedule and within budget, with first gold targeted for June 2027.

During July, the company completed bulk earthworks for infrastructure at the Laverton processing plant, which is designed for throughput of 1.5 million tonnes per annum (Mtpa).

The company reports earthworks for the raw and process water ponds, non-process infrastructure, and run-of-mine extension are nearing completion, while structural steel and platework installation has begun in the primary crushing area. Concrete foundations for the primary crusher, semi-autogenous grinding mill, carbon-in-leach tanks, and thickener have also advanced.

Brightstar executed power purchase and liquefied natural gas supply agreements during July. Engineering work on the associated power station and gas infrastructure continues, with major long-lead equipment secured.

The first two production bores have also been drilled and cased as part of the project’s borefield development.

Managing Director Alex Rovira says work during August will focus on the remaining earthworks, concrete pours, and plant infrastructure.

“Looking ahead to August, the focus is on completing the remaining bulk earthworks and major concrete pours, mobilising the CIL [carbon-in-leach] tank installation team, and commencing the next phase of steel fabrication and borefield infrastructure,” Rovira says.

Brightstar says the Goldfields Project is expected to produce an average of about 75,000 ounces of gold per annum over an initial six-year mine life. The company is also evaluating mine-life extensions and a potential increase in plant throughput to 2.5Mtpa.

Meanwhile, mining at the Second Fortune underground operation is scheduled to conclude in August, with ore stockpiles continuing to increase. Site preparation at the Lord Byron open pit is progressing ahead of targeted mobilisation during the December quarter.

A January 2026 Feasibility Study outlined about $1 billion in life-of-mine cash flow, a $606 million net present value, and a 74% internal rate of return.

Write to France Pinzon at Mining.com.au

Images: Brightstar Resources
Add to Watch List:
Author Image
Written By France Pinzon
France is an editor and writer with more than 15 years of experience in lifestyle media publishing, brand communications, and strategy. She has held senior editorial roles across print and digital publications and co-founded a boutique digital marketing agency. She is also a novelist and a collector of typewriters.