Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine
Silver Tiger Metals El Tigre Project in Mexico

Silver Tiger raises $87 million for El Tigre construction

Silver Tiger Metals (TSX:SLVR) has announced a C$87 million ($87.08 million) bought-deal financing as capital costs for its El Tigre Project in Mexico increase to US$124 million ($174 million).

The company has agreed with Stifel Nicolaus Canada and a syndicate of underwriters to issue 87 million units at C$1 each. Each unit comprises one common share and half a warrant, exercisable at C$1.35 per share for 24 months from closing.

Underwriters hold a 30-day over-allotment option for a further 15%, which could lift gross proceeds to about C$100 million. The offering is scheduled to close on or about 13 October 2026.

Net proceeds will fund exploration and development at the silver-gold project in Sonora, Mexico, plus working capital and general corporate purposes.

The updated capital expenditure estimate for the mine and process plant at the Stockwork Zone is about US$124 million, up US$37 million from the initial estimate in the company’s 2026 technical report.

That comprises about US$108 million under the engineering, procurement, and construction management contract with Kappes, Cassiday & Associates, Cassiday del Norte, plus US$16 million managed directly by Silver Tiger.

As at 10 September 2026, the company had contractually committed about US$81 million, or 66% of total estimated capex, and incurred about $US17 million towards those requirements.

Following the offering, Silver Tiger expects a pro forma cash balance of C$173 million, comprising C$90 million in current cash and C$87 million in gross proceeds, less C$4 million in underwriters’ commission.

After funding the estimated remaining capex of C$150 million, the company anticipates excess cash of C$23 million. If the over-allotment option is exercised in full, pro forma cash would rise to about C$185 million and excess cash to C$35 million.

CEO Glenn Jessome says construction is progressing toward production, adding that “commissioning and first pour are targeted for December 2027”.

Silver Tiger Metals is a Canadian silver-gold developer advancing a portfolio of precious metals and assets in Mexico.

Write to JC Villarba at Mining.com.au

Images: Silver Tiger Metals
Add to Watch List:
Author Image
Written By JC Villarba
JC is an editor with a decade of experience shaping digital content for worldwide audiences. He has spent time embedded in the construction industry, producing content for some of Australia's leading construction and equipment platforms. A Political Science graduate, he has developed a long-standing habit of following global affairs too closely. Outside of work, JC can be found behind a camera, hunting for a good meal, or deep in a book about film or history.