Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine

Maritana begins early works at Black Swan hub

Maritana Minerals (ASX:MRT) has commenced early works at its Black Swan Processing Hub (BSPH) in Western Australia, targeting first gold production in H2 2027.

The company has engaged GR Engineering Services (ASX:GNG) to deliver the 20-week early works program. Early works cover earthworks, demolition, detailed engineering, and long-lead equipment procurement.

This phase follows completion of the 2.5-million-tonne-per-annum front-end engineering and design (FEED) study in June 2026.

Maritana says the program aims to de-risk costs and scheduling ahead of full construction targeted for Q3 2026.

Managing Director Grant Haywood says the commencement of early works is a ‘major step forward’ for the BSPH.

“[The hub] will see site-based activities begin shortly as we transition from design to delivery,” Haywood says.

“GR Engineering Services will lead this phase, while detailed engineering and the ordering of long-lead equipment is progressed in parallel.

“These steps de-risk costs and timing, which keep us on track for our objectives of advancing toward full construction in Q3 CY2026 and producing first gold from the Black Swan Processing Hub in H2 CY2027.”

Maritana has also engaged Zeal Engineering as owner’s engineer (OE) to oversee delivery of the program.

Processing plant conversion

The scope covers converting the existing processing plant and building new areas at the BSPH.

Works include refurbishing the crushing and grinding circuit and converting the single-stage semi-autogenous grinding (SAG) mill circuit to a semi-autogenous ball mill crusher configuration.

Long-lead equipment procurement is currently progressing to maintain project schedules. Maritana has already ordered mill motors and thickeners.

Additionally, GRES has completed non-destructive testing of the SAG mill shell and head welds, identifying a small number of defects that will be resolved during the early works phase.

Full steam ahead towards full construction

Maritana says it has committed approximately $25 million for early works. These funds will go towards securing critical long-lead equipment and advancing detailed engineering ahead of the engineering, procurement, and construction (EPC) phase.

The program is expected to take about 20 weeks, targeting completion by early Q4 2026 as the company finalises contract arrangements with GRES.

Meanwhile, Maritana notes the EPC contract is being finalised, positioning the company for a seamless transition from early works into full construction ahead of a final investment decision.

The company also intends to award carbon-in-leach (CIL) circuit contracts during early works.

Maritana Minerals is an emerging mid-tier gold producer focused on developing the BSPH near Kalgoorlie-Boulder, Western Australia.

Write to Paula Fabe at Mining.com.au

Images: Maritana Minerals
Add to Watch List:
Author Image
Written By Paula Fabe
Paula has over 15 years of combined experience in PR, brand communications, and content marketing. She has experienced both agency and client sides of content ideation and production, mentoring young creatives along the way. She has also worked directly with small businesses in the Philippines, helping shape and refine their brand stories. Off-duty, she is co-founder of a brunch social for young women, building a community grounded in growth, connection, and mentorship. In her leisure time, she enjoys a strong cup of coffee and a good K-drama and spending time with her family.