Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine

Besra Gold edges towards production with EIA approval at Jugan Project, Malaysia

Besra Gold (ASX:BEZ) has received key local government approval for proposed test/pilot gold mining and processing at its Jugan Project in the Bau Goldfield corridor of Malaysia.

The company reports the Natural Resources and Environment Board (NREB) of Sarawak has approved an environmental impact assessment (EIA) for the planned mining and processing testwork.

The EIA, combined with supporting documentation regarding mine rehabilitation and pilot plant specification details, will now be lodged with the Land and Survey Department of the Ministry of Natural Resources and Urban Development for approval to begin mining activities within ML01/2013/1D.

Until formal approval is received from the Ministry of Natural Resources and Urban Development, Besra reports it will continue with preliminary activities under an Early Commencement Works approval granted in December 2022.

This includes ‘sterilisation drilling’ to ensure the proposed pilot plant infrastructure will not sterilise access to potential commercial mineralisation. In the meantime, the company reports the design of the pilot processing plant is largely complete, with procurement items sourced.

Besra also says arrangements are being advanced to engage civil engineering and fabrication contractors to ensure the build and commissioning of the operation meet the December 2023 schedule.

Additionally, the company says there are no exceptional conditions attached to the EIA approval, noting it was granted with general terms and conditions including quarterly reporting of environmental monitoring.

Besra says EIA approval is a long-lead-time item that is crucial for the construction and operation of the proposed test/pilot plant processing facility and associated mine pit. Initially, the plant will have a nominal throughput capacity of 50 tonnes per day, which can be expanded to 400 tonnes per day.

The plant will have a nominal throughput capacity of 50 tonnes per day, which can be expanded to 400 tonnes per day

The company reports this throughput range will ensure valid commercial scalability of the processing results, which will be incorporated into the final feasibility study for Jugan.

Besra Gold is an ASX-listed gold miner focused on exploring and developing the Bau Goldfield in East Malaysia. The company currently holds a 92% interest in the Bau Gold Project, which contains multiple brownfield exploration projects including Pejiru, Jugan Hill, Sirenggok, Bekajang, Taiton, and Say Seng.

Write to Harry Mulholland at Mining.com.au

Images: Besra Gold Inc

 

Add to Watch List:
Written By Harry Mulholland
Hailing from the Central Coast region of NSW, Harry is a passionate journalist with a background in print, radio and ESG news. When not bashing away on his keyboard, he can be found brewing a coffee or playing with his dog.