NevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plantStrategic Energy tests two Canobie targets NevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plantStrategic Energy tests two Canobie targets
Bannerman Energy Etango Uranium Project in Erongo, Namibia

Bannerman advances Etango uranium construction

Bannerman Energy (ASX:BMN) has reported that construction at its Etango Uranium Project in Erongo, Namibia, remains on budget and schedule.

The contractor workforce has exceeded 560 personnel and achieved 1.1 million lost‑time injury‑free hours.

Bulk earthworks are approximately 92% complete, focusing on the freshwater pond, wet plant terraces, and heap leach pad. Production of heap leach drainage aggregate continues, with approximately 29% of total requirements completed.

Concrete construction is advancing across key dry plant infrastructure areas, with 10,800m³ of concrete cast, representing approximately 60% of phase one and phase 2A packages.

CEO Gavin Chamberlain says the bulk earthworks contract is now more than 90% complete, a key achievement in “de-risking the critical path for full‑scale construction”.

The company achieved one million lost‑time injury‑free hours during May 2026, extending Bannerman’s unbroken 17‑year safety record. Four Namibian contractors deliver earthworks, civil construction, aggregate production, and infrastructure works across the site.

Civil and mechanical design for the dry plant stands at approximately 94% complete, aligning with schedule requirements for construction drawings.

Wet plant design remains on schedule for issuing construction drawings later this year, with detailed engineering approximately 28% complete.

Bannerman executed a permanent water supply agreement with NamWater in early June 2026, covering supply for the initial Etango‑8 development. The project targets an average production of 3.5 million pounds of uranium oxide annually for 15 years.

Phase one of the permanent water supply pipeline is approximately 87% complete. The company also signed a definitive power supply agreement with NamPower, with the detailed design of the dedicated feeder bay progressing.

Bannerman Energy expects to appoint the engineering, procurement, and construction management consultant in Q3 2026.

All contractors on site are Namibian businesses, including early works undertaken by local small and medium enterprises.

Write to JC Villarba at Mining.com.au

Images: Bannerman Energy

Add to Watch List:
Author Image
Written By JC Villarba
JC is an editor with a decade of experience shaping digital content for worldwide audiences. He has spent time embedded in the construction industry, producing content for some of Australia's leading construction and equipment platforms. A Political Science graduate, he has developed a long-standing habit of following global affairs too closely. Outside of work, JC can be found behind a camera, hunting for a good meal, or deep in a book about film or history.