Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine Apple’s iPhone boom highlights critical minerals powering smartphones•Presenting a united front for Queensland’s copper sector•Thailand seeks Myanmar mine access amid arsenic pollution•Egypt to set up state-backed company to license artisanal gold miners, free detainees•Brixton closes $7.4 million raise for Thorn, Langis projects•Heliostar banks record $78.7 million for Ana Paula push•Mining giants bet billions on 2030 supply crunch•Gunnison Copper reports Q3 output, revenue surge•Triumph Gold targets $15.46 million for Yukon push•African Rainbow Minerals faces a jobs dispute at Nkomati mine•Angola seeks 10% stake in De Beers under Anglo’s proposed exit•Gold price rebounds but heads for biggest weekly loss since June•Teck copper strike reaches BC port as operator sues union•Copper benchmark rocked by miner-smelter tug-of-war•Zimbabwe mining bill targets community, environmental safeguards•Mount Isa critical minerals hub secures Feasibility Study funding•Eramet initiates $814.5 million capital raise to reduce debt•Richemont backs natural gemstones, declines De Beers comment•‘Tis the season for administration as Comlek falls a second time•OceanaGold Philippines trials wireless blasting at Didipio mine
Austral Resources Rocklands Project

Austral drives ahead to Rocklands restart

Austral Resources (ASX:AR1) is pushing towards mine restart at the Rocklands Copper Project in North West Queensland, with its refurbishment program progressing on schedule and on budget.

The company has secured an as-new, unused 4.75-megawatt semi-autogenous grinding (SAG) mill, which will be delivered to the site in late July.

Austral has also undertaken detailed engineering assessments across the project’s existing process plant infrastructure. These covered primary crushing and ball milling; flotation circuits, thickening, and filtration; and concentrate handling facilities.

The company has also commenced a detailed review of mechanical equipment deemed capable of being repurposed in the revised process flowsheet. This includes screens, bins, pumps, hoppers, and associated equipment.

GR Engineering Services has been appointed to undertake engineering design and construction management for the front-end modifications required for the mine restart.

Front end engineering design activities began in early April and are expected to be completed by end-July 2026.

Assessment of conveyors and structures identified for demolition is underway. Demolition activities are expected to accelerate this month ahead of the SAG mill’s arrival, along with pebble crusher circuits.

The company expects to mobilise for earthworks and civil construction activities in Q3 2026, with completion targeted ahead of the 2026/27 wet season.

Austral has also completed a confirmatory drilling at Rocklands, with metallurgical core samples to be processed by Core Technologies.

The resulting testwork program is expected to optimise the flotation circuit design, recovery performance, and concentrate quality.

COO Shane O’Connell says that the company is focused on developing a “simpler, lower-risk, and capital-efficient processing circuit” that maximises copper concentrate production while leveraging the substantial infrastructure already in place at the project.

“Importantly, Rocklands will be supplied by ore from Austral’s wholly owned mining operations. Mining is already underway at Flying Horse and Mt Clarke, supplying oxide feed to Mt Kelly while exposing future sulphide feed for Rocklands, which will be blended with the existing Rocklands sulphide resource,” O’Connell says.

“This integrated approach provides a clear pathway from mining through to processing and positions Austral as a producer of both oxide and sulphide copper from its eastern and western operations.

“With engineering progressing, major equipment secured, and site works planned to commence in Q3 2026, we remain confident in delivering the Rocklands restart on time and on budget.”

Austral Resources is a copper cathode producer operating in the Mt Isa region in Queensland, Australia.

Write to Maddison Elliott at Mining.com.au

Images: Austral Resources
Add to Watch List:
Author Image
Written By Maddison Elliott
Maddison holds a Bachelor of Communication and Journalism, a Bachelor of Business, and a Master of Writing, Editing and Publishing. She enjoys transforming complex information into clear, engaging stories that inform, educate, and connect with readers. Outside of the newsroom, Maddison spends her time reading, exploring new places, catching a game, or spending time with friends and family.