Vault Minerals (ASX:VAU) has secured regulatory clearances for construction of the Southern Tailings Management Facility at its Sugar Zone mine in Ontario, Canada.
The Ontario Ministry of Energy and Mines formally filed the project’s closure plan amendment on 16 July, following its submission on 6 May.
Vault also received a final amended sewage environmental compliance approval from the Ministry of Environment, Conservation, and Parks on 22 July. The approval authorises the discharge of tailings into the new facility.
The Southern Tailings Management Facility is planned to serve as the mine’s sole tailings storage facility over the life of its current ore reserve.
Vault says the facility will provide a lower-cost operating model than the previous combination of dry-stack tailings and slurry deposition within the Northern Tailings Management Facility.
Vegetation clearing and logging at the site have been completed. The company says work during the 2026 Canadian summer construction season will include grubbing, dam foundation earthworks, drainage installation, and the development of access roads and laydown areas.
Vault also plans to construct diversion channels for non-contact water.
Primary dam construction and pipeline installation are scheduled for completion during the 2027 Canadian summer season.
Underground development at Sugar Zone began on 1 July. Waste rock generated during the 2027 financial year will supplement existing stockpiles and provide construction material for the dam.
The approvals form part of Vault’s preparations to restart the Sugar Zone gold mine. The company submitted the updated project permit in June to support the proposed restart.