At the International Mining and Resources Conference + Expo (IMARC) in Sydney on Wednesday (28 October), a key takeaway from the US delegation was how mining reforms could provide greater certainty for investors.
Speaking to the ‘From Policy to Projects’ panel, American Exploration & Mining Association (AEMA) Executive Director Mark Compton says the litigation phase in the mining permitting process is significantly slowing projects down.
“It obviously not only adds years to that particular project, but it just creates that uncertainty,” Compton tells the audience.
The litigation phase refers to the stage when project approvals, environmental impact statements, or federal and state permits are challenged in court by outside parties.
Challenges are usually filed by environmental groups and local communities, often targeting the US National Environmental Policy Act (NEPA), the Clean Water Act, or the Endangered Species Act.
“A lot of projects aren’t happening because we’re not attracting the investment because of the litigious nature of folks in the US,” Compton adds.
This is where the recently introduced Bipartisan American Affordability and Jobs Act of 2026 (BAAJA) comes in, with proposed measures to reduce project delays in the permitting stage.
Some judicial reforms raised in BAAJA include lowering the statute of limitations for certain challenges under NEPA from six years to 150 days, alongside changes to eligibility requirements for parties seeking to challenge project approvals.
Compton says he and the team at AEMA are pushing hard for this bill, as the “best time for permitting reform was decades ago”.
“From an industry association perspective, it’s our goal to make the US as attractive of a mining jurisdiction as we can. Obviously, having durable permitting efficiencies is a big part of that,” Compton says.
Encouraging investment
Administrative actions, such as the FAST-41 program, have played a big role in speeding up the processing phase.
In November last year, FAST-41 included as many as 50 mining and exploration projects on its dashboard. However, it’s not as safe as it seems.
FAST-41 falls under the Fixing America’s Surface Transportation Act Section 41, enacted in December 2015 to improve the speed, transparency, and predictability of federal environmental reviews and authorisations for large infrastructure projects.
Mining projects became eligible for coverage under FAST-41 in early 2021. However, that coverage is provided only by rule, Compton explains.
“Mining is still covered under that program only by rule. That means it can be taken away by rule,” he tells the audience.
“We have legislation out there to add mining statutorily to that FAST-41 program.”
Compton explains that the long duration of most permitting processes and the uncertainty that comes with them are what prevent investment, as “capital is going to go where certainty is provided”.
“This BAAJA, would probably be a good example. It’s the best chance that we’ve had for permitting certainty probably ever,” he says.
“We need to get this passed before the end of this Congress, so we’re going to be really focused on that for the next month or two. It’s going to come up after the election.”
Mining.com.au is a media partner of IMARC and attended the event throughout the week (27–29 October) at the International Convention Centre (ICC) in Sydney.
Write to Maddison Elliott at Mining.com.au