NevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plantStrategic Energy tests two Canobie targets NevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plantStrategic Energy tests two Canobie targets
Toubani Resources Kobada Gold Project in Mali

Toubani readies first drawdown as Kobada advances

Toubani Resources (ASX:TRE) is preparing for its first gold stream drawdown this month as construction advances at the Kobada Gold Project in Mali.

Construction remains on schedule, with process plant work commencing and key infrastructure either completed or nearing completion.

The water storage dam and turkey’s nest are finished, while the airstrip is 65% complete. In addition, accommodation camp construction is progressing, with foundations poured and walls under construction.

Carbon-in-leach (CIL) tank earthworks have been completed, with formwork set up for ring beams. Clearing at the crusher and run-of-mine pad is well advanced, along with tailings storage facility preparation where the company has commenced embankment construction.

“Development of the Kobada Gold Project continues to advance on schedule, with activities progressing across multiple work fronts, including the commencement of CIL tank construction,” Managing Director Phil Russo says.

“The award of key construction packages and mobilisation of personnel and contractors to site reflects the transition into an increasingly active phase of project execution.”

All key construction personnel and contractors have now mobilised to site, while fabrication and shipping of structural steel continue. The company reports more than 500 tonnes have been fabricated to date.

Meanwhile, ball mill fabrication is complete, with shipping imminent. Final inspection of generator sets is complete, which are being prepared for shipping.

All plate work for the CIL tanks has been received in Bamako, with rolling, bevelling, and painting in progress. The first completed plates will be shipped to site shortly once ring beams are poured and cured.

An update to the Kobada mineral resource estimate (MRE) has commenced and is expected to be completed in Q3 2026. The updated MRE will underpin final pit design and mine scheduling ahead of start-up.

Toubani is preparing for its first drawdown under the stream financing facility by the end of August, with monthly drawdowns scheduled thereafter. The company is also progressing an additional facility with AFG Bank and other financiers to enhance working capital.

First gold production is targeted for Q3 2027, with the company remaining on schedule.

Toubani Resources is a Perth-based gold development company advancing its flagship Kobada Gold Project in southern Mali towards production.

Write to JC Villarba at Mining.com.au

Images: Toubani Resources
Add to Watch List:
Author Image
Written By JC Villarba
JC is an editor with a decade of experience shaping digital content for worldwide audiences. He has spent time embedded in the construction industry, producing content for some of Australia's leading construction and equipment platforms. A Political Science graduate, he has developed a long-standing habit of following global affairs too closely. Outside of work, JC can be found behind a camera, hunting for a good meal, or deep in a book about film or history.