Nicola Mining (TSX-V:NIM) has completed its 2026 mining campaign at the Dominion Creek Gold Project in British Columbia, Canada, delivering approximately 1,300 tonnes of ‘high-grade’ mill feed to Merritt for processing.
Nicola expects material from Dominion and privately held Red Eye Resources, alongside feed processed for Blue Lagoon Resources (CSE:BLLG), to contribute to fourth-quarter revenue.
The Dominion campaign was scheduled to begin in early July but was delayed by the arrival of purchased equipment and additional mine development after previously unrecognised mineralised veins were identified.
Mining focused on three mineralised structures: the approximately 5m-diameter Pit Vein, the 1.5m-diameter 16 Vein, and the newly identified 16 East Vein.

Right: Excavators working at Dominion Gold. Source: Nicola Mining.
Nicola says the late-July deployment of a drilling unit mounted on an excavator improved extraction efficiency. With mine development complete and key equipment operational, the company believes Dominion is positioned for increased extraction and potential gold production in 2027.
CEO Peter Espig says Dominion has progressed from acquisition to mining within approximately three years.
“We have advanced Dominion Gold from acquisition through mine development and bulk-sample extraction, demonstrating the potential value of integrating selective mining opportunities,” Espig says.
The company says the identified veins remain open in several directions, while additional mineralised structures discovered during the campaign warrant further geological evaluation.
The delivery follows Nicola’s completion of processing material from Red Eye before preparing to receive Dominion feed, as previously reported by Mining.com.au.
Nicola Mining is a Canadian mining and exploration company that owns the Merritt processing facility. It holds a 75% economic interest in the first 10,000 tonnes from Dominion, increasing to 100% thereafter.
Write to France Pinzon at Mining.com.au
Main image: Nicola Mining