Rio Tinto pledges $369.9 million for Panguna•China rare earth producers’ profits surge on supply caps•Hindalco considers tripling copper recycling capacity•Chile weighs private partners for Codelco copper mines•Report flags illicit gold flows into UAE despite controls•Semirara coal mine auction raises Philippine supply concerns•Pope Leo condemns Amazon mining, deforestation•Australia wary of iron ore trade manipulation•Asia drives 73% of global nuclear growth•Partnerships, permitting, and potential in British Columbia•Many Peaks locks in $70 million for Ferké FID•Gorilla pounces on IGO’s Cosmos Project•Fed rate hike concerns continue to weigh on gold•Tungsten joins antimony and gold at Krakatoa’s Zopkhito Project•Rio Tinto invests in Weipa’s bauxite industry as exports rise•Legend completes Pyrophyllite Hill drilling, intersects pyrite•Aureka graduates from explorer to producer•Skylark finds broad gold beyond Ehuasso resource•Mammoth to secure stake in tungsten project amid supply chain push•Black Rock chases $103 million Mahenge cornerstone Rio Tinto pledges $369.9 million for Panguna•China rare earth producers’ profits surge on supply caps•Hindalco considers tripling copper recycling capacity•Chile weighs private partners for Codelco copper mines•Report flags illicit gold flows into UAE despite controls•Semirara coal mine auction raises Philippine supply concerns•Pope Leo condemns Amazon mining, deforestation•Australia wary of iron ore trade manipulation•Asia drives 73% of global nuclear growth•Partnerships, permitting, and potential in British Columbia•Many Peaks locks in $70 million for Ferké FID•Gorilla pounces on IGO’s Cosmos Project•Fed rate hike concerns continue to weigh on gold•Tungsten joins antimony and gold at Krakatoa’s Zopkhito Project•Rio Tinto invests in Weipa’s bauxite industry as exports rise•Legend completes Pyrophyllite Hill drilling, intersects pyrite•Aureka graduates from explorer to producer•Skylark finds broad gold beyond Ehuasso resource•Mammoth to secure stake in tungsten project amid supply chain push•Black Rock chases $103 million Mahenge cornerstone
Graphite One Graphite Creek

Graphite One clears Ohio anode plant air permit

Graphite One (TSX-V:GPH) has received the final air permit for the first phase of its planned active anode material (AAM) facility in Conneaut, Ohio, US.

The Ohio Environmental Protection Agency issued the 10-year permit to wholly owned subsidiary Graphite One (Ohio). It covers a 10,000-tonne-per-year synthetic graphite blending and coating plant with an estimated initial capital cost of US$80 million ($113.91 million), subject to revision after final engineering.

Effective from 27 October 2026, the approval covers agglomeration, carbonisation, feeding and blending, and finishing and packaging. Thermal oxidisers are designed to control 98% of volatile organic compounds, while baghouses target 99% particulate control.

Graphite One describes the permit as the project’s key environmental approval and the most demanding to obtain. Remaining requirements include standard state and local building, construction, and operating permits.

President and CEO Anthony Huston says the approval advances the company’s US supply-chain plans.

“Receiving the final Ohio air permit is an important step toward establishing a domestic synthetic anode material supply chain,” Huston says.

Construction decision targeted for 2027

Graphite One is completing final engineering and pursuing project financing. It targets a final investment decision (FID), award of an engineering, procurement, and construction contract, and the start of construction by April 2027.

The air permit requires construction to begin within 18 months of its effective date, with one possible 12-month extension. First synthetic graphite AAM sales are targeted for the December quarter of 2028, subject to financing, construction, and an FID.

The Export-Import Bank of the United States (EXIM) has issued an amended, non-binding US$1.4 billion letter of interest supporting potential expansion in 25,000-tonne increments to 100,000 tonnes annually. Two EXIM letters now cover potential support totalling US$2.07 billion.

Graphite One plans to supply natural graphite from its Graphite Creek Project in Alaska, where mine production is targeted for 2030. A federal permit decision is targeted under the FAST-41 timetable by 30 September 2027.

The permit follows Graphite One’s third US defence award for developing and testing domestically sourced advanced carbon materials.

Graphite One is a Canadian developer advancing an integrated US graphite supply chain spanning mining in Alaska and anode material manufacturing in Ohio.

Write to France Pinzon at Mining.com.au

Main image: Graphite One
Add to Watch List:
Author Image
Written By France Pinzon
France is an editor and writer with more than 15 years of experience in lifestyle media publishing, brand communications, and strategy. She has held senior editorial roles across print and digital publications and co-founded a boutique digital marketing agency. She is also a novelist and a collector of typewriters.