Graphite One (TSX-V:GPH) has received the final air permit for the first phase of its planned active anode material (AAM) facility in Conneaut, Ohio, US.
The Ohio Environmental Protection Agency issued the 10-year permit to wholly owned subsidiary Graphite One (Ohio). It covers a 10,000-tonne-per-year synthetic graphite blending and coating plant with an estimated initial capital cost of US$80 million ($113.91 million), subject to revision after final engineering.
Effective from 27 October 2026, the approval covers agglomeration, carbonisation, feeding and blending, and finishing and packaging. Thermal oxidisers are designed to control 98% of volatile organic compounds, while baghouses target 99% particulate control.
Graphite One describes the permit as the project’s key environmental approval and the most demanding to obtain. Remaining requirements include standard state and local building, construction, and operating permits.
President and CEO Anthony Huston says the approval advances the company’s US supply-chain plans.
“Receiving the final Ohio air permit is an important step toward establishing a domestic synthetic anode material supply chain,” Huston says.
Construction decision targeted for 2027
Graphite One is completing final engineering and pursuing project financing. It targets a final investment decision (FID), award of an engineering, procurement, and construction contract, and the start of construction by April 2027.
The air permit requires construction to begin within 18 months of its effective date, with one possible 12-month extension. First synthetic graphite AAM sales are targeted for the December quarter of 2028, subject to financing, construction, and an FID.
The Export-Import Bank of the United States (EXIM) has issued an amended, non-binding US$1.4 billion letter of interest supporting potential expansion in 25,000-tonne increments to 100,000 tonnes annually. Two EXIM letters now cover potential support totalling US$2.07 billion.
Graphite One plans to supply natural graphite from its Graphite Creek Project in Alaska, where mine production is targeted for 2030. A federal permit decision is targeted under the FAST-41 timetable by 30 September 2027.
The permit follows Graphite One’s third US defence award for developing and testing domestically sourced advanced carbon materials.
Graphite One is a Canadian developer advancing an integrated US graphite supply chain spanning mining in Alaska and anode material manufacturing in Ohio.