Leo Lithium returns to ASX amid turbulence

Leo Lithium (ASX:LLL) resumed trading on the Australian Securities Exchange (ASX) today (4 September 2023) following several weeks of voluntary suspension but it has not roared back into action.

Shares in Leo Lithium were down 51.32% to $0.56 as of 12:35pm AEST following news of several ongoing issues at the company’s flagship Goulamina Lithium Project in Mali.

The resumption of trading follows a two-day trading halt from 18 July, followed by a voluntary suspension from 20 July until this morning.

Suspension of DSO

Chief among the hurdles at Goulamina — Leo Lithium’s sole asset — is a directive from Mali’s Ministry of Mines to suspend the direct shipped ore (DSO) component of activities.

As recently as 30 June, Leo Lithium had been targeting 185,000 tonnes per year of DSO exports until spodumene production begins, saying that the haulage process would also help define the optimum handling solution.

Though no clear reason was given for the directive, Leo Lithium says it has submitted information to the Mali government outlining both the DSO operations and the potential benefits to the country from DSO sales. No formal response to the submission has yet been received, but the company was quick to note that mining is continuing in line with the pre-existing plan, although its previous guidance on 2023 and 2024 DSO production and sales had been withdrawn.

Managing Director Siman Hay says: “While Leo Lithium had a preference to bring Goulamina DSO product to market in advance of our expected spodumene concentrate production in the first half of 2024, it is not necessary for a successful project, and we did not consider a DSO opportunity in our feasibility studies.”

Tax issues

Located roughly 150km by road from Mali’s capital city Bamako, the Goulamina Project is held by Leo Lithium through a 50% stake in Mali Lithium BV (MLBV), in which Ganfeng Lithium Group (SHE:002460) holds the remaining 50% interest. MLBV owns Lithium du Mali SA (LMSA), which in turn owns the Goulamina Project.

LMSA’s relationship with the country is governed by an agreement that was transferred to the company when it acquired the project, and which Leo Lithium claims the Mali government has failed to honour. 

Under the agreement, LMSA is exempt from duties and taxes on petroleum products used to generate energy for the extraction, transport and processing of ore. It’s also entitled to a 3-year exemption from import duties and taxes on equipment for the project.

“Since mid-July 2023, the government’s actions have not been consistent with the project’s exemptions from import duties and taxes for the importation of equipment,” the company says in an announcement this morning.

“Leo Lithium did not receive any communication of this change.”

To date, the company has paid US$4 million ($6.2 million) in import duties and taxes, and expects to rack up another US$16.1 million ($24.94 million) this quarter if the issue is not resolved.

As a result, the total estimated exposure for LMSA regarding “unplanned” import duties and taxes amounts to between US$45 million and US$50 million (between $69.71 million and $77.45 million).

Association with Firefinch

There is also some contention over Leo Lithium’s association with Firefinch (ASX:FFX), which owns the Morila Gold Mine in Mali, and from which Leo Lithium was spun-out in early 2022.

“For clarity, Leo Lithium is not considering any future involvement in Morila

“Leo Lithium and Ganfeng have presented information to the Commission” — set up by the Mali Government to handle the issues — “that conclusively shows that Leo Lithium and Ganfeng have no connection with Firefinch (other than Firefinch holding a 17.6% shareholding in Leo Lithium with no board representation), that the Goulamina licence was validly transferred from a Firefinch entity to LMSA, and that Leo Lithium and Ganfeng were not involved with the Morila Gold Mine at any time,” the company says.

“For clarity, Leo Lithium is not considering any future involvement in Morila.”

New mining code

Central to these issues, however, could be a new mining code that was rolled out by Mali’s interim President Assimi Goita last week. Leo Lithium says it has commenced a review of the code and will advise of any impacts.

President Goita overthrew 2 previous presidents in 2020 and 2021 during coups spurred by anger at the handling of an Islamist insurgency, which has only worsened since his junta took power. He has said he will organise elections and restore power to civilians in 2024.

Under the new code, the military-led government will be able to increase its ownership of gold concessions and recoup what it says are major shortfalls in production revenues. That ownership is currently capped at 20%, but will be increased to up to 35%, potentially doubling the sector’s contributions to GDP in the process.

Mali’s Finance Minister Alousseni Sanou said last week that an audit of the mining sector had shown the state was missing 300 billion to 600 billion CFA francs ($768 million to $1.54 billion), which it intends to recover.

It’s not yet known whether the new code will affect existing projects, but a mining ministry official told Reuters recently that it would depend on the implementing decrees, which are yet to be made available.

Cooperation agreement with Ganfeng

But it’s perhaps not all bad news. Leo Lithium finalised a cooperation agreement with Ganfeng on September 3, outlining a range of “long-term strategic benefits”

They include raising the proposed stage two capacity to 500,000 tonnes per year, which would lift overall capacity at Goulamina to 1 million tonnes per year, and evaluating the potential to co-invest in a downstream conversion facility in Europe, or another region within reasonable distance of West Africa.

As such, the original strategic placement agreement will be replaced by an equity investment agreement, underwhich Ganfeng will fund US$137.2 million ($212.16 million) worth of costs at Goulamina in exchange for new shares in MLBV. Ganfeng will then earn up to a 55% stake in MLBV, with Leo Lithium holding the remaining 45% as operator and manager of the joint venture.

Despite the issues, Leo Lithium says construction and mining activities remain on schedule, and that delays due to custom duties are recoverable

The only material change to come from this restructuring is that offtakes for any potential stage three expansion will reflect the new equity positions. That is, Leo Lithium will be entitled to 45% of stage three offtake, as opposed to 50%.

Despite the issues, Leo Lithium says construction and mining activities remain on schedule, and that delays due to custom duties are recoverable.

The project was estimated to be roughly 35% complete at the end of July, but this is expected to accelerate with additional contractors on site over the next few months.

As of June 30, Leo Lithium had $67.1 million in cash, while the Goulamina JV had US$60.5 million ($93.55 million). This is in addition to a US$40 million ($61.85 million) undrawn debt facility, the drawdown of which is expected to begin this month.

Write to Oliver Gray at Mining.com.au

Images: Leo Lithium
Author Image
Written By Oliver Gray
Originally from Perth, Oliver has a keen interest long-form journalism. He has written for a number of publications and was most recently Contributing Editor of The Market Herald’s opinion section, Art of the Essay.

Leo Lithium prepares for stage one production at Goulamina Project area, Mali

Leo Lithium (ASX:LLL) remains on schedule to produce its first spodumene product in June 2024 after producing run-of-mine ore from its Goulamina Project in Mali over Q2 2023.

The company, which has a $1.36 billion market capitalisation, reports the first blast on site took place in June 2023, with initial mining activities focused on the stage one starter pit. The starter pit contains 1.65 million tonnes (Mt) of undiluted fresh ore of the measured resource category at an average grade of 1.68% Li2O and 0.73% Fe2O3. 

Meanwhile, mining contractor Corica Mining Services is ramping up activities on-site. The initial pit has been prepared, with the first bench completed. Leo says over 196,000 bcm of material has been mined and this ore is being stockpiled.

Commenting on the quarterly activities, Leo Lithium Managing Director Simon Hay says: “Our Goulamina Lithium Project remains on schedule, and construction activities are underway. Mining has commenced, with initial mining activities focused on the stage one starter pit, leading to production and stockpiling of our first run of mine ore.”

Mining has commenced, with initial mining activities focused on the stage one starter pit, leading to production and stockpiling of our first run of mine ore”

In addition, Leo’s Goulamina joint venture (JV) company entered into a binding agreement with Bambara Resources SARL and Kodal Minerals during the June quarter to acquire 100% of 2 new mineral concessions in Mali for US$2.5 million plus a 2% gross royalty. 

The Mafele West and Nkemene West concessions are set to nearly triple the land area of the Goulamina Project from 101km-square to 287km-square. 

Leo says the increased landholding will enable the joint venture company to optimise the location of infrastructure and mining stockpiles over the long term and will be especially useful for the stage two expansion. 

As of 30 June 2023, the company held $67.1 million cash at hand, and the Goulamina JV held $60.5 million cash at hand, according to its June quarterly report. 

Leo says construction activities are on track, with engineering and drafting about 80% complete so far. 

In addition, the company says drill results that did not make the cut-off date for the June Mineral Resource Estimate (MRE) update are expected in the coming months. 

Leo also notes that exploration and infrastructure sterilisation drilling is planned to restart after the wet season. Through future exploration drilling, the company intends to focus on potential resource extensions along strike and down-dip of the optimised ‘reasonable prospects for eventual economic extraction’ (RPEEE) pit shell, as well as increasing the confidence level by converting inferred to indicated material within the pit shell. 

During the June quarter, the company entered into a strategic placement with Ganfeng to raise $106.1 million through the issue of 131 million new fully paid ordinary Leo Lithium shares. 

Proceeds from the placement ensure Leo is fully funded for its stage one development costs and operational ramp-up costs for the Goulamina Project. 

Leo Lithium is a pure-play lithium exploration company developing its Goulamina Lithium Project in Mali. The company intends to be West Africa’s first spodumene producer when the project comes online in 2024 to supply the booming lithium-ion battery industry.

Write to Aaliyah Rogan at Mining.com.au

Images: Leo Lithium Ltd
Author Image
Written By Aaliyah Rogan
Relocated from the East Coast in New Zealand to Queensland Australia, Aaliyah is a fervent journalist who has a passion for storytelling. When Aaliyah isn’t writing stories, she is either spending time with friends and family or down at the beach.

The Weekly Wrap-Up 22 June, 2023

Mining.com.au is Australia’s leading online daily Mining news service, reaching hundreds-of-thousands of mining professionals, investors, and industry participants each month. The Weekly Wrap-Up with Harry Mulholland provides listeners with a recap of the mining headlines each week.

In this episode, Harry reports on news from Leo Lithium (ASX:LLL), Hamelin Gold (ASX:HMG), Barton Gold (ASX:BGD), and Solis Minerals (ASX:SLM).

Written By Italic BoldDev

Leo Lithium awards Corica Mali $520 million mining services contract for Goulamina Project

Pure-play lithium developer Leo Lithium (ASX:LLL) has awarded a $520 million open-pit mining services contract for its Goulamina Project to Corica Mali, a subsidiary of Corica Mining Services. 

Leo, which has a $1.43 billion market capitalisation, says the contract encompasses 6 months of pre-production activities at Goulamina followed by a fixed 5-year term. 

This contract award follows the completion of a ‘competitive’ tender process and ‘extensive’ due diligence based on safety, experience capability, equipment availability, and cost. 

Leo notes the scope of the contract comprises grade control, drill and blast, load and haul, and plant ore feed services, with a planned material movement target of between 18 million to 20 million tonnes per annum over the term. 

With this contract now awarded, Corica is reported to have already mobilised to site under an early works contract and has moved forward with undertaking pre-strip and direct shipped ore (DSO) mining and crushing services.  

LLL

Addressing the contract, Leo Lithium Managing Director Simon Hay says: “We are delighted to appoint Corica as our mining services contractor following an intensive tender process. Corica has a long history and strong presence in Mali and will bring substantial local employment and supplier opportunities to the region. 

With the mining contractor now in place, Leo Lithium has taken another major step towards realising its target of first spodumene concentrate production in H1 2024″

With the mining contractor now in place, Leo Lithium has taken another major step towards realising its target of first spodumene concentrate production in H1 2024. We look forward to working with Corica over the long term, commencing with DSO activities this quarter.”

Leo Lithium is an ASX-listed developer focused on its world-class Goulamina Lithium Project in Mali. According to the company, the project represents the next lithium project of ‘significant’ scale to enter production and is poised to be the first of its kind in West Africa. 

Leo Lithium had $71.2 million cash at hand of 31 March 2023, as stated in its latest quarterly report.

Write to Adam Drought at Mining.com.au

Images: Leo Lithium Ltd
Author Image
Written By Adam Drought
Born and raised in the UK, Adam is a sports fanatic with an interest in Rugby League and UFC/MMA. When not training in Muay Thai and Brazilian Jiu Jitsu, Adam attends Griffith University where he is completing his final year of a Communication & Journalism degree.

Changes for Mining Industry Roll Out in July: Mining Minute June 30

Moving into July, Western Australia’s new Aboriginal Cultural Heritage Act will come into effect, as well as Federal Government reforms to its Safeguard Mechanism to cap carbon dioxide emissions to reach reduction targets. Plus, news from Leo Lithium (ASX:LLL) in today’s Mining Minute

Author Image
Written By Carolyn Rebeiro
Joining Mining.com.au from the West Coast, finance presenter Carolyn began her journalism degree in Townsville and developed a passion for mining news after a FIFO stint in WA's Goldfields.

Leo Lithium produces first DSO at Goulamina Lithium Project in Mali

West Africa-focused lithium miner Leo Lithium (ASX:LLL) has produced its first direct shipped ore (DSO) at its equally owned Goulamina Lithium Project shared with Ganfeng (SHE:002460) in Mali.

The company reports the first blast on site was initiated earlier this month. Initial DSO mining activities have focused on the stage one starter pit that contains 1.65 million tonnes of undiluted fresh ore in the measured resource category at an average grade of 1.68% Li2O and 0.73% Fe2O3.

The stage one starter pit is centred on the Main pegmatite domain, which formed part of the recently upgraded Goulamina mineral resource. The starter pit will enable the mining process to be optimised and provide reconciliation data that will be integrated into the ore reserve update, which is scheduled to be completed in August 2023.

The early works and DSO crushing contractor, Corica Mining Services, is methodically ramping up activities on site. Additionally, the starter pit for the DSO operation has been prepared with the first bench completed, as the crusher and associated equipment performs to a ‘high’ standard.

Leo reports it will award the contracts for the haulage of DSO imminently, while a robust due diligence process has finalised following the issue of the trucking tender in April.

The company says the process involved several local contractors of ‘high-calibre’ with a ‘comprehensive’ site visit completed by Leo, while logistics experts confirmed the quality of the fleet and capability.

Discussions are also advancing with the Port of San Pedro in Côte d’Ivoire to act as an additional port option to the Port of Abidjan in Côte d’Ivoire.

Leo says the DSO haulage process will give it insights to define the ‘optimal’ materials handling solution ahead of spodumene concentrate production, which is on schedule to begin in the first half of 2024.

First revenue from DSO is on track to be received during Q4 2023, and Leo Lithium anticipates the export of DSO ore for 6-9 months in advance of spodumene production. On an annualised basis, Leo is targeting 185,000 tonnes of DSO exports until spodumene production begins in the first half of 2024..

“The early start-up of the open-pit mining operations at Goulamina via DSO is a positive milestone that positions the company to crystallise long-term benefits”

Commenting on the production of DSO, Leo Lithium Managing Director Simon Hay says: “The early start-up of the open-pit mining operations at Goulamina via DSO is a positive milestone that positions the company to crystallise long-term benefits.

The revenue potential during a solid pricing environment will bolster our balance sheet flexibility as we continue to progress the Goulamina Project towards spodumene concentrate production over 2 stages. DSO also presents an opportunity for us to optimise our logistics solution as we scale up Goulamina, further de-risking the project’s development.”

Leo Lithium is an ASX-listed explorer focused on developing the Goulamina Lithium Project in Mali. The company says the project will be the first of its kind in West Africa when production begins in the first half of 2024. Additionally, the project is set to produce 506,000 tonnes per annum under stage one, increasing up to 831,000 tonnes per annum under stage two.

On 29 May 2023, Leo Lithium executed a strategic placement with Ganfeng to raise $106.1 million. Proceeds from the strategic placement will ensure Leo Lithium is fully funded for its share of Goulamina stage one development and operational ramp-up costs. Additionally, Leo is well-positioned to progress its various co-commitments with Ganfeng as part of the cooperation agreement.

Write to Harry Mulholland at Mining.com.au

Images: Leo Lithium Ltd
Written By Harry Mulholland
Hailing from the Central Coast region of NSW, Harry is a passionate journalist with a background in print, radio and ESG news. When not bashing away on his keyboard, he can be found brewing a coffee or playing with his dog.

Leo Lithium bolsters Goulamina mineral resource to 211 million tonnes, Mali

Spodumene mine developer Leo Lithium (ASX:LLL) has increased the Mineral Resource Estimate (MRE) at its Goulamina Lithium Project in Mali by 48.2%.

The company reports the updated MRE of 211 million tonnes @ 1.37% lithium oxide for 2.89 million tonnes of lithium oxide was informed by a resource definition drilling campaign undertaken over the second half of 2022 and the first half of 2023.

The updated MRE incorporates all historical data and recent drilling data completed up to 5 June 2023, and the Danaya and Northeast domains have also been updated in this MRE.

Leo commissioned independent resource consultancy CSA Global to update the MRE, which resulted in the classification of measured, indicated, and inferred mineral resources. The reported resources in this MRE are constrained below the Top of Fresh Rock (TOFR) surface and are reported within a US$1,500 optimised pit shell.

The company says mineralised pegmatite material within the optimised pit shell is considered to have ‘reasonable prospects for eventual economic extraction’ (RPEEE).

Leo reports the updated MRE provides scope for further exploration potential, as ‘large’ parts of the resource remain open along strike and at depth, and it sets the foundation for a new ore reserve estimate scheduled to be completed in August 2023.

Additionally, the company says the MRE update is ‘encouraging’ ahead of accelerated Direct Shipping Ore (DSO) revenue in Q4 2023 and first spodumene production in the first half of 2024.

Leo reports only material below the TOFR surface is reported as part of the MRE. Future drilling is planned for after the upcoming wet season and will focus on resource extensions along strike and down-dip, outside the optimised RPEEE put shell. This drilling will also aim to convert inferred material to the indicated category within the pit shell.

Commenting on the updated MRE, Leo Lithium Managing Director Simon Hay says: “We are excited to report a very significant resource upgrade which confirms the outstanding scale, high-grade nature, and further growth potential of the Goulamina Project.

An increase at Goulamina of 68.6 million tonnes from a very moderate drilling campaign is a fantastic outcome”

An increase at Goulamina of 68.6 million tonnes from a very moderate drilling campaign is a fantastic outcome. Furthermore, there is scope for additional growth as the deposit remains open at depth and along strike, creating new drilling targets for the geology team.

This significant upgrade also supports the possible extension of the 23-year mine life of the Goulamina Project and the recent cooperation agreement with Ganfeng. A key aspect of the cooperation agreement is for Leo Lithium to conduct an engineering study into raising Goulamina Stage Two capacity to 500,000 tonnes per annum, lifting overall Goulamina to 1 million tonnes per annum of spodumene concentrate.

Results from the MRE upgrade will flow into the planned ore reserve estimate upgrade, which is scheduled for completion in August 2023. These results are also encouraging ahead of first spodumene concentrate product in Q2 2024 and the early revenue opportunity from the targeted export of direct shipping ore in H2 2023.”

Since the last published MRE on 17 January 2023, Leo has completed an additional 30,853m of reverse circulation (RC) and 9,719m of diamond drilling at an estimated cost of US$5 million. 

Significant intercepts include GMDD033 with 134.89m @ 1.63% Li2O from 99.96m and 59.16m @ 1.58% Li2O from 252.4m; GMRC703 with 141m @ 2.15% Li2O from 81m; and GMRC705 with 158m @ 1.33% Li2O from 118m.

The company says drilling has identified several new pegmatite domains and extended existing domains along strike to the north and down-dip. These dykes are modelled over about 3,000m of strike with individual dyke widths up to 100m.

Leo Lithium is a Perth-based explorer developing the Goulamina Lithium Project in Mali, which is held in a 50/50 joint venture (JV) between Leo and China-based Ganfeng Lithium (SHE:002460). The project is forecast to produce 502,000 tonnes per annum of spodumene concentrate under stage one production, which will increase to 831,000 tonnes per annum under stage two.

Write to Harry Mulholland at Mining.com.au

Images: Leo Lithium Ltd
Written By Harry Mulholland
Hailing from the Central Coast region of NSW, Harry is a passionate journalist with a background in print, radio and ESG news. When not bashing away on his keyboard, he can be found brewing a coffee or playing with his dog.

Leo Lithium sinks claws into $106 million strategic placement to advance Goulamina Project in Mali

ASX-listed Leo Lithium (ASX:LLL) has struck a deal with GFR International (Ganfeng) (SHE:002460) to raise $106.1 million to support the development of the Goulamina Lithium Project in Mali.

Under the agreement, Leo will issue 131 million new shares at $0.81 to raise the funds, representing 9.9% of Leo’s total pro-forma shares on issue. This offer price represents a 6.5% premium to the company’s 5-day volume weighted average price (VWAP) of $0.76 per share up to and including 26 May 2023.

The company reports the new shares will be issued in a single tranche and will rank equally with existing shares on issue. Once the placement is complete, Ganfeng will hold a 9.9% interest in Leo, while other substantial holder Firefinch (ASX:FFX) will retain a 15.9% interest in the company.

Shares in Leo Lithium have spiked 14.48% to $0.83 at 11:10 am AEST.

Leo reports it has agreed to several co-commitments with Ganfeng that will be documented in a cooperation agreement, including a stage 2 capacity expansion, downstream cooperation, and an offtake for Goulamina.

As part of the stage 2 capacity expansion at Goulamina, both companies agree to undertake a study to expand the Goulamina production capacity to about 500,000 tonnes per annum. This will increase the combined capacity of Goulamina stage 1 and 2 to 1 million tonnes per annum. The companies will jointly fund the study and examine opportunities to expedite the timing of stage 2.

Leo also reports it will conduct and manage a feasibility study into a joint downstream conversion facility in Europe or a region within a reasonable distance of West Africa. Both companies will fund this study, and Leo notes it will be responsible for finding a suitable location, identifying and engaging with potential partners, and economic analysis.

Ganfeng will be responsible for analysing conversion technology, considering the application of its existing technology to the downstream facility, and leading the engineering and design for the construction of the downstream facility.

Further, with a larger production capacity and potential for a downstream conversion facility, Leo and Ganfeng have agreed to amend their lithium offtake agreement in regard to stage 2 production.

Ganfeng will have offtake rights to 350,000 tonnes per annum for the life of mine, while Leo will have offtake rights to 150,000 tonnes per annum for the life of mine.

Ganfeng will also process 150,000 tonnes per annum of its offtake in China on a permanent basis, while the remaining 200,000 tonnes per annum will be processed in China until a joint downstream conversion facility with Leo is established in Europe or elsewhere.

Meanwhile, Leo’s 150,000 tonnes per annum will be tolled in China by Ganfeng until the downstream conversion facility is available to process the product. If the agreement is not reached on a downstream conversion facility within 5 years from the date of this agreement, then Leo is free to deal with its 150,000 tonnes per annum offtake for Goulamina stage 2 as it sees fit.

Commenting on the placement, Leo Lithium Managing Director Simon Hay says: “The strategic placement and terms of the proposed cooperation agreement with Ganfeng represent a transformational opportunity for Leo Lithium and provide further validation of the tier-1 quality of Goulamina, including the significant potential upside of our development pathway.

By utilising the tolling arrangement with Ganfeng, Leo Lithium stands to benefit from Ganfeng’s existing strong market relationships and technical reputation, enabling enhanced cost savings and operational efficiencies in tolling the Goulamina stage 2 product to lithium hydroxide.

This is an exciting chapter for Leo Lithium, with a number of near-term deliverables also underway”

This is an exciting chapter for Leo Lithium, with a number of near-term deliverables also underway, including our first spodumene product in 2024 and accelerated revenue from direct shipped ore (DSO) with shipments planned in the fourth quarter of this year. We are proud to be partnering with Ganfeng, who are a recognised global leader across the lithium value chain, and look forward to continuing to build on our strong existing relationship.”

Subject to the ore reserve estimate for Goulamina being upgraded sufficiently in Q3 2023, and potentially future upgrades, Leo and Ganfeng have also agreed to investigate the opportunity for a further expansion of Goulamina in a third stage.

Under stage 3, both companies agree to form a jointly funded exploration joint venture (JV) to focus on Australia initially. This agreement is not exclusive and will not interfere with Ganfeng’s exploration ventures.

Leo Lithium is an ASX-listed company focused on bringing its Goulamina Lithium Project into production in the first half of 2024. The project lies in Mali and is held in a 50/50 JV between Leo and Ganfeng.

Write to Harry Mulholland at Mining.com.au

Images: Leo Lithium Ltd
Written By Harry Mulholland
Hailing from the Central Coast region of NSW, Harry is a passionate journalist with a background in print, radio and ESG news. When not bashing away on his keyboard, he can be found brewing a coffee or playing with his dog.

Leo Lithium pounces on resource growth opportunities at Goulamina Lithium Project in Mali

Pure-play lithium company Leo Lithium (ASX:LLL) has encountered further thick ‘high-grade’ mineralisation outside the current resource in a drilling program at its Goulamina Lithium Project in Mali.

The company reports exploration reverse circulation (RC) drilling is continuing at the project, with further results from the Northeast and Danaya domains expected throughout Q2 and into Q3 2023. Leo also expects an updated Mineral Resource Estimate (MRE) for Goulamina to be released before the end of the June 2023 quarter.

The company says results from 41 drillholes completed at the Danaya Domain are continuing to demonstrate ‘excellent’ grades while also remaining open at depth and along strike.

The mineral resource at Goulamina is constrained within an RPEEE (Reasonable Prospects for Eventual Economic Extraction)-optimised pit shell. Leo says additional mineralisation identified outside the pit shell can potentially increase the mineral resource.

‘Significant’ results recorded at the Danaya Domain include GMRC689 with 92m @ 2.01% Li2O from 132m, including 36m @ 3% Li2O from 132m; GMDD013 with 112.7m @ 1.43% Li2O from 83.2m; and GMDD014 with 82.8m @ 1.54% Li2O from 153.2m.

Meanwhile, results have been received for 16 RC and diamond drillholes that intersected thick ‘high-grade’ spodumene pegmatite dykes at the Northeast Domain.

Leo reports spodumene is the only lithium-bearing mineral phase recognised, and notes mineralisation remains open along strike and down-dip.

‘Significant’ results recorded at the Northeast Domain include GMRC597D with 60.35m @ 1.72% Li2O from 205.3m and 14m @ 2.17% Li2O from 271m; GMRC613D with 39m @ 1.98% Li2O from 74m; GMRC694 with 46m @ 1.45% Li2O from 112m; and GMRC693 with 64m @ 1.38% Li2O from 102m and 27m @ 1.73% Li2O from 187m.

Commenting on the results, Leo Lithium Managing Director Simon Hay says: “The latest results show excellent intercepts and grades outside the current pit shell. With the potential to grow the mineral resource outside the current project area, the opportunity to unlock further value from the outstanding Goulamina asset continues to be apparent.

With the potential to grow the mineral resource outside the current project area, the opportunity to unlock further value from the outstanding Goulamina asset continues to be apparent

With drilling continuing, we remain on track to update the Mineral Resource Estimate for Goulamina in late June and release a reserve upgrade in August.

Our project also remains on schedule for first spodumene concentrate product in late H1 2024, and early revenue materialising from the DSO (direct shipping ore) in the second half of this year.”

Leo Lithium is a pure-play lithium company focused on developing its Goulamina Lithium Project in Mali. Goulamina is scheduled to deliver its first spodumene concentrate by mid-2024 to supply the lithium-ion battery industry.

The project is held in a joint venture with Chinese chemical producer Ganfeng (SHE:002460), with both companies holding a 50% interest. Once in production, Goulamina will be the first spodumene producer in West Africa.

Write to Harry Mulholland at Mining.com.au

Images: Leo Lithium Ltd
Written By Harry Mulholland
Hailing from the Central Coast region of NSW, Harry is a passionate journalist with a background in print, radio and ESG news. When not bashing away on his keyboard, he can be found brewing a coffee or playing with his dog.

Leo Lithium outlines plans to lunge towards spodumene production at Goulamina Project in Mali

Leo Lithium (ASX:LLL) reports development is on track to deliver the first spodumene production in Q2 2024 at its 50% owned Goulamina Joint Venture (JV) Project in Mali. 

As reported in the company’s mid-term review, after declaring a Final Investment Decision (FID) in January 2022, the company began detailed design, procurement, and construction activities at Goulamina in February 2022, and the project is now 20% completed. 

Additionally, Leo reports the project is now more than 50% of the way through the 27-month construction phase. Leo notes it has ‘significantly’ progressed the project since the completion of the DFS in December 2021. 

The company conducted a revised capital cost and reports that given the construction of the project still has a further 12 months to run, an additional contingency of US$25 million has also been included in the capital costs, resulting in an overall increase in capital costs of US$30 million to US$285 million, which is a 12% increase. 

As construction activities at Goulamina increase, the company has costed new plans associated with the operational readiness phase, which is focused on workforce readiness, the ramp up on mining activities, and the beginning of plant commissioning activities to produce the first spodumene. 

Additionally, the company notes this phase is expected to cost an additional US$33 million and is driven by a more comprehensive costed plan for commissioning spodumene production in Mali. 

Commenting on the progression of the project and capital costs, Leo Lithium Managing Director, Simon Hay says: “After conducting a thorough review of the project’s capital costs, expected capital increases were identified due to market conditions and an accelerated mining ramp-up. 

“After conducting a thorough review of the project’s capital costs, expected capital increases were identified due to market conditions and an accelerated mining ramp-up”

These include optimising the stage one plant design to enhance the plant’s performance, making necessary scope changes for stage two, and responding to industry-wide inflationary pressure. 

Despite these cost changes, Leo Lithium remains extremely well-positioned to take advantage of high spodumene prices in the next 3 to 5 years. 

Looking ahead, we are encouraged to see early revenue from the targeted export of direct shipped ore (DSO) by Q4 2023, further demonstrating our commitment to delivering value as a top-tier, low-cost producer.”

The total project capital from FID to the first production in Q2 2024 is expected to be US$318 million. 

Additionally, Leo states there is an early revenue opportunity from DSO, which is confirmed at an expanded 185,000 tonnes, providing ‘significant’ additional early funding. 

Mining activities are set to begin in May 2023 and will supply ore for DSO and the stockpile build ahead of plant commissioning. 

The company adds it is expected that by the end of May 2023, the construction management team will have completed a detailed review of plans based on the productivity of existing contractors and supply vendors. 

In addition, proposed delivery plans will be available for the mechanical and electrical installation contractors. 

The Goulamina Project is a JV project between Leo Lithium and Chinese mining company Ganfeng Lithium Group which holds the remaining 50%. 

The project represents the next lithium project of ‘significant’ scale to enter production and is one of the ‘largest’ and ‘lowest’ capital intensity lithium spodumene projects globally with a stage one capacity of 506,000 dry tonnes per annum. 

Leo Lithium is a pure-play lithium company focused on developing its Goulamina Lithium Project in Mali, West Africa. 

Images: Leo Lithium Ltd
Author Image
Written By Aaliyah Rogan
Relocated from the East Coast in New Zealand to Queensland Australia, Aaliyah is a fervent journalist who has a passion for storytelling. When Aaliyah isn’t writing stories, she is either spending time with friends and family or down at the beach.

Leo Lithium on the hunt to expand mineral concessions footprint in Mali

Leo Lithium (ASX:LLL) has entered into a binding agreement with unlisted company Bambara Resources and Kodal Minerals (LON:KOD) to acquire 2 mineral concessions in Mali.

The company reports it will acquire 100% of the Mafele West and Nkemene West concessions through its 50% owned joint venture (JV) company shared with Chinese company Ganfeng Lithium (SHE:002460), Goulamina JVCo for a consideration of £2.5 million and a 2% gross royalty.

The 2 concessions are owned by Bambara as part of its Bougouni Lithium Project. In 2019 Kodal was granted exclusive access rights for mineral exploration activities and an option to acquire an 80% legal and beneficial interest in the concessions

Under the agreement, in the event of an economic mineral discovery on the area of the concessions and that discovery is supported by a Bankable Feasibility Study (BFS), then on the granting of a mineral exploration licence over the area, the vendors (Bambara and Kodal) will have the right to be issued an equity carried interest level of 15% for no initial consideration.

Leo map

The Goulamina JVCo has no obligation to expend a minimum of $250,000 over 2 years on mineral exploration activities on the concessions. Leo reports limited exploration has been conducted on the concessions to date, and also notes a recent site inspection by its geologists observed pegmatite boulders on the surface.

Commenting on the agreements, Leo Lithium Managing Director, Simon Hay says: “We are pleased to have acquired these concessions. The Goulamina Project has a 23-year mine life and this is likely to grow due to the very large increase in the Danaya resource announced on 17 January 2023.

“The Goulamina Project has a 23-year mine life and this is likely to grow due to the very large increase in the Danaya resource announced on 17 January 2023”

This increased land holding will enable the Goulamina JVCo to optimise the location of infrastructure and mining stockpiles over the long term and this will be especially useful for our stage two expansion. 

Our initial plans for the concessions are to sterilise drill areas needed for near-term infrastructure and stockpiling and then to develop an exploration program for the remaining area, to be implemented in future years. The concessions have had scant exploration to date and the Goulamina area has shown to be very prospective for lithium mineralisation.”

Leo reports all parties have reached agreement of all terms and notes a binding agreement has been signed for the Mafele West concession that has been recently renewed. The process to transfer Mafele West from Bambara to the Goulamina JVCo will begin immediately and is expected to take a number of weeks.

Meanwhile the final binding agreement for Nkemene West will be executed when the renewal documentation for the concession is received. Currently, the company says the renewal has been accepted by the Direction Nationale de la Géologie et des Mines (DNGM) of Mail, and was recommended renewal with the final documents at the Mali Minister of Mines office pending signature.

The company says the Nkemene West agreement will be executed and the transfer will begin when the renewal is received.

Leo Lithium is an ASX-listed pure play lithium company focused on developing the Goulamina Lithium Project in Mali. The company says Goulamina will be the first hard rock lithium project in West Africa when it enters production in the first half of 2024.

Images: Leo Lithium Ltd
Written By Harry Mulholland
Hailing from the Central Coast region of NSW, Harry is a passionate journalist with a background in print, radio and ESG news. When not bashing away on his keyboard, he can be found brewing a coffee or playing with his dog.

Leo Lithium roars with further positive drilling results at Goulamina Project, Mali

Pure play lithium company Leo Lithium (ASX:LLL) has recorded further ‘high-grade’ results in a resource drilling program at the Goulamina Lithium Project in Mali.

The company reports the resource drilling program at Goulamina is aiming to increase the confidence level of the orebody, as well as converting a ‘significant’ amount of inferred resources into the indicated resource category.

An additional objective is to increase the overall resource base at the project, and Leo notes progress to meeting both objectives remains on plan. Leo says drilling is ongoing and has entered a new phase focused on testing potential northern strike extensions.

Leo reports further drilling results are expected in the coming months, and an updated MRE for Goulamina is expected before the end of the June 2023 quarter.

The company says exploration RC drilling and sterilisation drilling is continuing with a single RC rig. Further drilling results from the NE and Danaya domains will be reported once they have been received and reviewed throughout Q2 2023.

At the NE Domain, Leo reports a ‘substantial’ reverse circulation (RC) and diamond drilling program has been completed. The company says assays for 59 RC holes have been received, and notes assays for the diamond core tails are still pending and will be released to the market when they become available.

‘Significant’ RC results include hole GMRX599D with 71m @ 2% lithium oxide (Li2O) from 18m; GMRC555 with 54m @ 1.48% Li2O from 64m; and GMRC579D with 62m @ 1.77% Li2O from 48m.

Commenting on the results, Leo Lithium Managing Director, Simon Hay says: “The latest set of results from our ongoing drilling campaign are again set to enhance the already high-quality Goulamina resource.

The Li2O grades received from the combined Danaya and NE Domain targets are overall higher than the current average Mineral Resource Estimate (MRE) grades for Goulamina.

“This is a fantastic result and positions us to deliver a robust MRE upgrade by the end of the current half year”

This is a fantastic result and positions us to deliver a robust MRE upgrade by the end of the current half year. With the high-grade mineralisation remaining open along strike, there is further growth potential ahead as we test potential northern strike extensions this quarter.”

Leo also reports that results have been received from 15 drillholes at the Danaya Domain. The company says new diamond core results show ‘excellent’ grades and pegmatite down-dip continuity.

The Danaya pegmatites are open at depth and along strike, while thick ‘high-grade’ downhole intercepts below the current reasonable prospects for eventual economic extraction (RPEEE) optimised resource pit shell have demonstrated the down-dip potential of Danaya.

‘Significant’ results recorded at Danaya include GMRC534D with 115.7m @ 1.74% Li2O from 147.6m; GMDD016 with 73.5m @ 1.64% Li2O from 199.17m; and GMDD019 with 37.2m @ 1.62% Li2O from 116.2m.

Leo Lithium is an Australian pure-play lithium company developing the Goulamina Lithium Project in Mali. Goulamina is expected to come online in 2024 to supply lithium to the lithium-ion battery industry. Once this occurs, Leo will be West Africa’s first spodumene producer.

Images: Leo Lithium Ltd
Written By Harry Mulholland
Hailing from the Central Coast region of NSW, Harry is a passionate journalist with a background in print, radio and ESG news. When not bashing away on his keyboard, he can be found brewing a coffee or playing with his dog.

Leo Lithium takes pride in validating DSO haulage routes for Goulamina Lithium Project

Leo Lithium (ASX:LLL) has made ‘substantial’ progress to defining optimal materials handling solutions to deliver both direct shipping ore (DSO) and spodumene concentrate from its Goulamina Lithium Project in Mali.

Leo Lithium reports it has achieved key milestones on logistics to deliver both materials from its joint venture (JV) Goulamina project in Mali to ports in Côte d’Ivoire.  The company reports that it seeks production by H1 2024.

The company notes inspections and discussions have confirmed the suitability of the San Pedro Port in the west of Côte d’Ivoire to act as a secondary port, with Leo Lithium’s senior management driving the entire route from mine site to port in late March. 

It is reported that this trip confirmed the quality of the road access between the site and port was of a ‘high standard’ and suitable for transporting bulk materials at the required rate.

Leo Lithium says the improved road conditions, in conjunction with the efficient border crossing at Niougoni means that potential exists to reduce the cycle time for the round trip from site to port and return from the 6 days as assumed in the Definitive Feasibility Study (DFS).     

First revenue from the DSO opportunity remains on track for H2 2023. 

Commenting on the validation of haulage routes, Leo Lithium Managing Director, Simon Hay, says: “With the trucking routes extensively assessed and a port provider secured, we have further de risked the development of the DSO opportunity as well as first concentrate production from Goulamina in 2024 and I look forward to updating the market on further details around our proposed DSO operations in the coming months.

“With the trucking routes extensively assessed and a port provider secured, we have further de risked the development of the DSO opportunity as well as first concentrate production from Goulamina in 2024…”

The San Pedro and Abidjan ports are both well-run operations, with the potential for backload at both options set to deliver enhanced cost efficiencies and give us substantial flexibility in our haulage operations.

Pleasingly, we have received significant interest from numerous capable and established trucking contractors for the trucking tender and we expect to finalise the trucking contract in the near-term.”

The company also notes nominal payloads for its proposed trucks have increased by 32% to 50 tonnes from 38 tonnes that was the basis of the DFS. Leo believes the increase in payload, combined with better-than-expected road conditions will reduce absolute truck numbers required, as well as potentially generating enhanced cost efficiencies. 

Additionally, tenders have been issued and confirmed for 5 West African-based trucking contractors to transport the DSO material from site to both the Adibjan and San Pedro ports. Completion of review of the tenders is expected to occur by the end of April, with all contractors able to deliver DSO material to the port by Q3 of CY2023.  

With discussions having been initiated with the Port of San Pedro, Leo Lithium announces it will continue to proactively evaluate other potential port options, with Dakar, Senegal expected to be assessed once resolution has been reached with San Pedro. 

Leo Lithium is an ASX-listed pure-play lithium company focused on developing its world-class Goulamina Project alongside its JV partner Ganfeng Lithium Group (SHE:002460). The project is equally owned by both parties and represents the next lithium project of ‘significant’ scale to enter production, making it the first of its kind in West Africa.

Images: Leo Lithium Ltd
Author Image
Written By Adam Drought
Born and raised in the UK, Adam is a sports fanatic with an interest in Rugby League and UFC/MMA. When not training in Muay Thai and Brazilian Jiu Jitsu, Adam attends Griffith University where he is completing his final year of a Communication & Journalism degree.

Leo Lithium changes address with new digs in West Perth

Leo Lithium (ASX:LLL) reports that the company’s registered office and principal place of business have changed as of today. 

The company’s new address has changed to Level 2, 16 Ventnor Avenue in West Perth.

Leo Lithium is developing the ‘world-class’ Goulamina Lithium Project, located in Mali. The pure-play hard rock lithium project will be the first of its kind in West Africa. 

Goulamina Process Plant Layout

The project is being developed in a 50:50 joint venture (JV) with Ganfeng Lithium Group Co., Ltd., the world’s ‘largest’ lithium chemical producer by production capacity. Ganfeng is providing funding, offtake, and operational support to de-risk development. 

Construction is currently underway and the first production is targeted for H1 2023. 

Leo Lithium is an ASX-listed and FRA-listed pure-play lithium company. The company will become West Africa’s first spodumene producer once its joint venture Goulamina project comes online in 2024 to supply the ‘booming’ lithium-ion battery industry. 

Images: Leo Lithium Ltd
Author Image
Written By Aaliyah Rogan
Relocated from the East Coast in New Zealand to Queensland Australia, Aaliyah is a fervent journalist who has a passion for storytelling. When Aaliyah isn’t writing stories, she is either spending time with friends and family or down at the beach.

Lycopodium full-year revenue on track to top $320 million amid ‘busy and rewarding’ period

Mining and engineering services firm Lycopodium (ASX:LYL) has generated revenue of $159.9 million and net profit after tax (NPAT) of $20 million for the 6 months to 31 December 2022.

Perth-headquartered Lycopodium reports that with a robust portfolio of projects and studies in delivery, the company is well placed to return a strong financial result for FY2023, with full-year guidance of about $320 million in revenue and NPAT in the order of $40 million.

The firm’s Managing Director Peter De Leo says the company is in the process of delivering a significant portfolio of projects across the globe, including mobilising to site on several major projects over the past 6 months, in addition to being awarded a number of new projects and studies.

“It has therefore been a very busy and rewarding period for the company, reflected in the strong results achieved at half-year”

“It has therefore been a very busy and rewarding period for the company, reflected in the strong results achieved at half-year.”

Projects at or nearing completion include the Bomboré Gold Project (Orezone) in Burkina Faso, which achieved first gold pour in September 2022; the Navachab Plant Expansion (QKR) in Namibia, which was completed in December 2022; the Motheo Copper Project (Sandfire) in Botswana and Cobré Ball Mill 6 Project (Minera Panama SA) in Panama, which are due for completion during Q1 2023; and the Séguéla Gold Project (Fortuna Silver Mines) in Côte d’Ivoire, with works on track for first gold pour mid-2023.

De Leo adds: “Pleasingly, we have already moved on to the next stage of development on a couple of these projects, including the Bomboré Expansion Study and the commencement of detailed engineering design works for the 5.2Mtpa Motheo Expansion Project.”

Works are continuing to schedule on a number of ongoing projects, including the Mine Services Area Relocation Project and Chemical Grade Processing Plant #3 (Talison Lithium) in Western Australia, the Batu Hijau Expansion Project (PT Amman Mineral Nusa Tenggara) in Indonesia, and the commencement of onsite works at the Ahafo North Project in Ghana (Newmont).

New awards involving the provision of Engineering, Procurement, Construction and Project Management services during the period, include the Kiaka Gold Project (West African Resources) in Burkina Faso, the Kathleen Valley Lithium Project (Liontown Resources) in Western Australia, the Goulamina Lithium Project (Leo Lithium) in Mali, the Sabodala Massawa Expansion Project (Endeavour Mining – Sabodala Gold Operations SA) in Senegal and the Lafigué Gold Project (Endeavour Mining – Lafigué Project) in Côte d’Ivoire.

Lycopodium works with clients to provide integrated engineering, construction, and asset management solutions. It delivers complex, multidisciplinary projects, through to the provision of feasibility studies and advisory services. Operating across the resources, infrastructure and industrial processes sectors, Lycopodium offers a diverse team of industry experts to deliver bespoke and innovative solutions across all commodity types.

With the capability to deliver projects around the world, the firm has offices in Australia, South Africa, Canada, Ghana, and the Philippines.

Write to Adam Orlando at Mining.com.au

Images: Lycopodium Ltd
Author Image
Written By Adam Orlando
Mining.com.au Managing Editor Adam Orlando has more than 20 years’ experience in the media having held senior roles at various publications, including as Asia-Pacific Sector Head (Mining) at global newswire Acuris (formerly Mergermarket). Adam has worked in newsrooms around the world including Hong Kong, Singapore, London, and Sydney.

Leo Lithium: on track to deliver a top tier mine in the booming lithium market

This article is a sponsored feature from Mining.com.au partner Leo Lithium Holdings Ltd. It is not financial advice. Talk to a registered financial expert before making investment decisions.

“Success occurs when opportunity meets preparation.”

Those words from late American author and motivational speaker Zig Ziglar are as apt as any to describe the journey of emerging lithium miner Leo Lithium (ASX:LLL).

Leo Lithium is developing the ‘world-class’ Goulamina Project in Mali – a pure-play hard rock lithium project, which will be the first of its kind in West Africa.

Goulamina is being developed in a 50:50 joint venture with Ganfeng, China’s largest lithium chemical producer, which is providing funding, offtake, and operational support to de-risk development.

Knowing that Goulamina is one of the few global spodumene projects with financial investment decision (FID) approved and in the execute phase, Managing Director Simon Hay explains pending success all comes down to preparation.

The outlook for Leo Lithium looks incredibly powerful – Goulamina has thick pegmatite intercepts, is open at depth and along strike, meaning there is scope for the resource to continue growing.

The MD explains that while construction works continues to ramp up on site with delivery of key equipment to now start, Leo Lithium has been working on many aspects in parallel to take Goulamina to the next level.

“We’re active on all different fronts. We’re active on geology, mine planning, on the project”

“We’re active on all different fronts. We’re active on geology, mine planning, on the project. We’re now pushing into the operational side of things, we’re engaging with the Mali community and government, we’re engaging trucking contractors, and we’re engaging stakeholders in Côte d’Ivoire as well as Mali. The maturity of the company and the whole project is advancing at a meticulously planned rate and it’s on track.”

The Goulamina Project also remains on budget, with engineering and design advancing and the construction supervision team now on site, with updated and detailed construction plans to be provided in Q2 2023.

Leo Lithium intends to expand Goulamina production in stage two to about 831,000 tonnes per annum of spodumene production after stage one is fully operational, based on the first five years of steady state stage two production. Early conceptual works are getting underway and an outline of the project plan is expected to be announced in H2 2023. This work will in part inform the execution strategy and plan for stage two.

Hay notes that in order to develop Goulamina stage one Leo Lithium needed a management team with technical, operational experience across lithium and West Africa. Experienced Perth-based executive Ron Chamberlain was appointed Chief Financial Officer (CFO) and Joint Company Secretary.

Mining engineering executive Tim Richards recently joined as Chief Operating Officer. With over 20 years of mining experience including in West Africa, he has worked across multiple projects in Ghana and Mauritania, as well as in South Africa.

Meanwhile, Alan Rule was appointed as Non-Executive Director, and follows the resignation of Mark Hepburn. Rule has covered the role of CFO for a number of ASX-listed mining companies with operations and projects in Australia and Africa including Galaxy Resources, a lithium producer. At a board level, Rick Crabb was appointed Non-Executive Chairman. He brings over 30 years of high-level mining experience in Australia and Africa.

LLL

Parallel planning

With the A Team now secured, Hay says that maintaining the project’s planned schedule is paramount.

The MD explains that the project schedule continues to outline a 27-month construction and commissioning timeline, which started in February 2022. The critical path continues to run through concreting, installation of the ball mill, supply, and installation of plant buildings, and electrical services. The installation of the overland water piping package from Sélingué Dam is now being designed (after ground truthing) and will remain a key area of focus due to the importance of providing site process water.

All areas of the plant are planned to undergo mineral commissioning in Q2 2024 culminating in the first product towards the end of the quarter. The production ramp up schedule will be further refined over the next 3 months and will be a key responsibility of Chief Operating Officer Tim Richards.

During the 2022 resource definition drilling campaign, Leo Lithium drilled 60 reverse circulation (RC) holes (including 6 pre-collar RC holes) for 9,292m and 17 diamond (DD) holes (including 6 diamond tails) for 3,428m. In Q4 2022, significant intersections were reported at the Danaya Domain with resource drilling revealing thick, ‘high-grade’ spodumene intercepts, followed by further ‘high-grade’ drilling results.

Since the last published Mineral Resource Estimate (MRE) on 20 July 2020, the Danaya mineral resource has increased by more than 150% to 56.1Mt @ 1.24% Li2O. The indicated resource classification at Danaya expanded by 213% to 24.4Mt @ 1.34% Li2O, and the total Goulamina resource base increased by 31% from 108.5Mt @ 1.45 % Li2O to 142.3Mt @ 1.38% Li2O.

While such an upgrade is impressive, Hay chimes in that he had already flagged it would happen for over a year, so the move had not come as much of a surprise to most investors.

Drilling at the Northeast Domain is ongoing with one reverse circulation (RC) rig and one diamond (DD) rig on site, with a further resource update targeted for about June 2023 following a 31% upgrade in the existing JORC compliant resource in mid-January, the MD notes.

Once the resource drilling is completed, Leo Lithium will then move onto geotechnical and sterilisation drilling.

“These drill results are fantastic, and that resource update takes us to 142 million tonnes of resource and we’re clearly in the top 10 and we’ll be approaching the top 5 scale spodumene resources globally. So, it’s becoming clearer each day that Goulamina is a terrific globally significant deposit.

From there we will look at the reserve. We’ll then hand it over to the mining engineers and they’ll look at the upgraded resource and then reshape the mine plan. We’d then expect some conversion of that new resource into reserve to grow our life of mine beyond 23 years.”

Plant design, engineering, and drafting

In total, about 80% (by value) of EPCM tender packages have been issued to vendors so far.

Leo Lithium awarded Lycopodium the contract for engineering and procurement (EP) and associated project management (PM) services for the Goulamina Project stage one. Valued at some $22.7 million, the EP and PM contract will be executed over the next 12-18 months. The project transport and logistics contract has been awarded to coincide with the planned completion of manufacturing or supply of various goods. The first shipments are expected to arrive on site during the current quarter.

The concrete installation, steel, and platework fabrication contracts were awarded during the December quarter.

DSO the way to go!

Hay notes that detailed planning has started into how its stage one product will be transported from mine site to port and eventually to end users. He says Leo Lithium is now assessing trucking contractors to move the spodumene concentrate from mine to port, which is most likely to be in Côte d’Ivoire, where the company has signed a 10-year contract for the storage and ship-loading of concentrate. While it’s still early days with first spodumene concentrate product on track for Q2 2024, the company will require a fleet of about 250 trucks over a 6-7-day cycle when at full rate.

In advance of spodumene production, Leo Lithium is examining the export of Direct Shipped Ore (DSO).

Hay says the reasons for pursuing DSO were obvious.

“We’re looking at DSO because one, the price is so positive that we can make a good margin exporting DSO. Secondly, it enables us to commission some parts for the project early. Rather than wait until mid-2024 we can bring some aspects forward including drill and blast, mining, and crushing. That’s all tested this year and not next year.

“So, with that preparation time we get to optimise and refine it and learn early. De-risking project ramp-up, it’s important”

So, with that preparation time we get to optimise and refine it and learn early. De-risking project ramp-up, it’s important. And thirdly, a key one of course is bringing forward revenue. If we didn’t do DSO our first revenue wouldn’t come until mid-2024, this can accelerate it by 6, 9, maybe even 12 months. And fourth, the market needs the lithium feedstock.”

Early stage planning has been completed targeting two 30,000 tonne DSO shipments in Q4 2023. The mine schedule and starter pit concept were developed with the DSO area demarcated from the construction activities so as not to impact the stage one schedule. Early engagement with various operational contractors has commenced with a view to understanding acceleration options and early mobilisation. Leo Lithium’s JV partner Ganfeng is supportive of the concept and interested in purchasing the DSO, Hay adds.

Leo Lithium will use the DSO operation as a means of assessing trucking contractors before appointing a contractor for the longer term business of spodumene transport.

Hay adds: “With DSO we haven’t yet worked out the exact trucking frequency but it could probably be half of spodumene trucking rate. If we get to start at a slower rate, we start with a less valuable product, so it’s a great way to test that part of the operation as well.”

In essence, the earlier and more prepared Leo Lithium engages the trucking contractor the more time it has to iron out any kinks when transporting the product from Goulamina ramps up.

The initial focus on product transport logistics is centred on analysing the regional bulk haulage market in the preferred transport corridor from the Goulamina site to Abidjan, Côte d’Ivoire. The Abidjan Port is the critical seaport and one of the most prominent African deep-water ports. It also serves as a transhipment hub for Mali and Burkina Faso but is located some 1,000km from Goulamina.

The 10-year contract provides port access and services, including product unloading, storage and ship loading of Goulamina spodumene concentrate product at the Abidjan Port. The agreement stipulates a minimum product throughput of 250,000tpa, with product receival and export to start from 1 July 2023.

Hitting the ground running

In parallel with that, major site works are also underway, including the pioneer camp and services commissioned. As part of the pioneer camp construction, 73 modular buildings were built, and the mobilisation of the first teams occurred during the period.

Earthworks activities have advanced in the plant area (including the grinding, magnetic separation, flotation, reclaim, and primary crusher areas) and the tailings storage facility (TSF) in line with the plan. This results in multiple work fronts now available for concrete activities including the temporary construction offices and permanent accommodation, which will occur in Q1 2023.

Hay notes that Leo Lithium will have equipment delivered to site likely by the end of the current quarter.

“We placed orders last year, that equipment is being fabricated now in China and Asia, and we’re having some of our team inspecting completed equipment. The team was in China to inspect the ball mill and now it’s completed it needs to be boxed up and put on a ship to Mali. There’s a whole bunch of equipment coming late this quarter and into the second quarter that we’re well and truly prepared for.”

ESG starts with community

Leo Lithium has now contracted a senior Environmental, Social and Governance (ESG) professional to develop a Sustainability Program in 2023. Initial tasks include conducting a materiality assessment, choosing an ESG framework and preparing the company’s first sustainability report.

The company continues to work on developing strong ties with local communities. Company representatives from the Community Department meet regularly with the communities to provide updates on the project including upcoming impacts as well as opportunities for employment and supply of goods and services, as outlined in the Stakeholder Management Plan.

At the end of Q4 2022, about 120 community members were employed on the Goulamina Project and 100% of unskilled jobs were held by Malians, on average 70% of the skilled jobs were held by Malians and 50% of supervisors were Malians.

The MD notes: “Our workforce is growing on site, so now we have over 400 contractors and staff on site. Of those 400, about 120 are locals from villages just 20-30km from site. This time last year we had maybe 15 employed and 3 months ago it was about 70 and now it’s 120. It’s growing and that translates to an economic benefit to the community, which is already starting.”

The company has also committed to improving access to water in the 4 local villages near the mine by installing potable water distribution systems.

“That’s being designed at the moment and will be rolled out in the middle of the year. We want to do that because Goulamina is the first substantial project in a long-term partnership that we’ll have with the government and the local community. And ESG is incredibly important to our organisation and our way of working.”

“Through sheer preparation, and the aim of becoming West Africa’s first lithium producer, we remain on track of first spodumene production by H1 2024″

Meanwhile, the Environmental and Social Impact Assessment (ESIA) was approved as part of the Exploitation Permit in 2019 and has a validity period of 30 years. The ESIA has been updated to reflect minor changes to the Project and this will be submitted to Malian  authorities in the current quarter.

Leo Lithium has a lot going on, yet through diligence, organisation, and meticulous preparation the company is seamlessly advancing its Goulamina Project in a burgeoning but not yet mature lithium market.

Hay notes: “Through sheer preparation, and the aim of becoming West Africa’s first lithium producer, we remain on track of first spodumene production by H1 2024, alongside the accelerated revenue opportunity from our Direct Shipped Ore in 2023.”

Write to Adam Orlando at Mining.com.au

Images: Leo Lithium Ltd
Author Image
Written By Adam Orlando
Mining.com.au Managing Editor Adam Orlando has more than 20 years’ experience in the media having held senior roles at various publications, including as Asia-Pacific Sector Head (Mining) at global newswire Acuris (formerly Mergermarket). Adam has worked in newsrooms around the world including Hong Kong, Singapore, London, and Sydney.