Congo says China’s Huayou unit must pay compensation despite halt•BHP and Rio shares face test as copper prices stumble•Brazil names 27 critical minerals amid domestic processing push•Purecore sharpens uranium-copper hunt with geophysicist•Column: Tin price hit by AI stock rout despite physical market tightness•Congo says US minerals deals should be judged by projects•MP Materials rare earth operations ‘no longer reliant’ on China•SAGA joins Canada’s business advocacy network, minerals council•Gold price slips following strong US nonfarm payroll print•Nutrien to close White Springs after earnings miss•Hindustan Zinc signs 11 Rajasthan park MoUs•Kazakhstan plans uranium reserve, signs Asian contracts•Indonesia eases FX retention rules for more miners•Physical gold demand rises in India ahead of Diwali•Graycliff five-for-five on Shakespeare gold drilling•Canada’s Budget 2026 fuels mining ambitions•Millions of hectares of exploration opens up in Colombia amid lifting restrictions•Aureos to deliver next phase of UK nuclear plant decommissioning•Minaurum wraps Alamos drilling with Africa find•US backs 6K with $361 million commitment for cathode plant Congo says China’s Huayou unit must pay compensation despite halt•BHP and Rio shares face test as copper prices stumble•Brazil names 27 critical minerals amid domestic processing push•Purecore sharpens uranium-copper hunt with geophysicist•Column: Tin price hit by AI stock rout despite physical market tightness•Congo says US minerals deals should be judged by projects•MP Materials rare earth operations ‘no longer reliant’ on China•SAGA joins Canada’s business advocacy network, minerals council•Gold price slips following strong US nonfarm payroll print•Nutrien to close White Springs after earnings miss•Hindustan Zinc signs 11 Rajasthan park MoUs•Kazakhstan plans uranium reserve, signs Asian contracts•Indonesia eases FX retention rules for more miners•Physical gold demand rises in India ahead of Diwali•Graycliff five-for-five on Shakespeare gold drilling•Canada’s Budget 2026 fuels mining ambitions•Millions of hectares of exploration opens up in Colombia amid lifting restrictions•Aureos to deliver next phase of UK nuclear plant decommissioning•Minaurum wraps Alamos drilling with Africa find•US backs 6K with $361 million commitment for cathode plant
Chute Technology

Chute Technology unveils the hidden costs of downtime

Engineering firm Chute Technology reveals that there are more costs for mine operators when it comes to downtime than just repairing equipment or getting a plant back up and running.

Senior Materials Handling Engineer Gian Naldi says the cost of downtime varies from plant to plant, but is regularly tens of thousands of dollars an hour.

“If you add this up over a week, month, or year, fixing the root cause of the problem becomes far more attractive than constantly treating the symptoms,” Naldi says.

Chute Technology says that it has become widely accepted that the operational symptoms of downtime can become part of the normal operating environment. Data on the causes and cumulative impact may exist, but properly verifying and analysing it is often a job that gets pushed down the priority list.

As such, the engineering firm has spent more than a decade tackling some of the toughest materials handling challenges in the mining, resources, mineral processing, and ports industries.

Naldi says that when spillage or other types of downtime occur, operators are looking for a quick solution. This usually involves getting conveyors, chutes, and other equipment as quickly as possible to restart production.

However, he says that if operators are not addressing the root cause of the problem, it will come back and cost more.

“And it’s often not known that there’s a more permanent fix available, with a quick return on investment (ROI), frequently under one month,” Naldi notes.

What to look for

Chute Technology reveals that there are several things to look for when seeking to debottleneck material flow and solve recurring issues.

These include the location of the belt or pulley, chute design, and consideration of the entire process.

Many chutes were designed several decades ago when maximum throughput was up to 1,000 tonnes per hour. After multiple plant upgrades to increase capacity, some sites find the chutes are not keeping pace. Operators tend to spend hours trying to track conveyors or adjust skirtboards to limit spillage, when the root cause is elsewhere.

Chute Technology says the chute design itself can also be an issue, involving factors such as the angle, drop height, uneven loading of conveyors, liner material, and skirtboard wear.

For example, wet, sticky coal will behave differently to iron ore or hard rock.

Chute Technology uses advanced simulation software to model how material flows through the chute before anything is fabricated. This ensures the design can be proven before installation.

Meanwhile, operators sometimes only focus on the problem area rather than the entire process. If one area has excess spillage or wear, it can be tempting to look at fixing just that location.

Chute Technology conducts entire site audits to identify underlying inefficiencies within transfer and materials handling systems. This includes problems that have developed over time or have never been fully addressed.

What flow optimisation delivers

Chute Technology has first-hand experience of how quickly ROI can be achieved when downtime is reduced and throughput is increased.

In one coal mining operation, the company installed a new coal chute with self-cleaning flow surfaces, reducing downtime from 700 minutes per month to just 10.

Naldi says this particular mine was able to save 11.5 hours of downtime per month, which equated to an extra 23,000 tonnes of throughput.

“That’s an additional 23,000 tonnes of product that was able to make it through the plant each month,” he says.

Another example was when Chute Technology assessed a mine that calculated downtime was costing the company $53,000 per hour. To address issues, the company opted to shut the plant down for a full eight-hour shift before resuming production.

“That means an eight-hour shutdown was costing them more than $400,000, and if they had to do this for several days in a row, the value of lost production could have paid for an entire new chute in under a week,” Naldi adds.

Chute Technology aims to provide materials handling solutions for bulk handling equipment across underground operations, railheads, and ports.

Write to Aaliyah Rogan at Mining.com.au

Main image: Chute Technology

Author Image
Written By Aaliyah Rogan
Originally from New Zealand, Aaliyah brings several years of experience covering the resources sector, with a focus on companies, commodities and global mining markets. Her reporting has spanned European markets and the evolving global mining landscape, with a focus on the stories and market forces driving change across the sector.