Battery metals project developer Arizona Lithium (ASX:AZL) has confirmed the ‘extremely low’ projected operating costs of its Prairie Lithium Project in Saskatchewan, Canada, through a new Pre-Feasibility Study (PFS).
The PFS is based on planned Phase One production from the project of 6,000 tonnes per annum (tpa) of lithium carbonate equivalent (LCE), and Arizona has posted predicted annual operating costs of US$2,189 per tonne over the life of the project. According to the company, these ‘exceptional’ economics make Prairie one of the lowest-cost projects on the globe.
Arizona, which has a $117.53 million market capitalisation, has presented a base-case pre-tax net present value (NPV) for the project of US$448 million over its 20-year mine life and an internal rate of return (IRR) of 23.9%, assuming a discount rate of 8% and a ‘conservative’ lithium price forecast of an average US$21,000 per tonne.
What’s more, the company says recent resource upgrades for the project suggest that its 20-year commercial operating life represents less than 3% of the indicated resource of 4.5 million tonnes of LCE.
Arizona has pegged construction and commissioning costs for the Phase-One, 6,000 tpa project at US$290 million. From here, each additional well pad is expected to cost US$70 million to install but will add production of around 2,000 tpa of LCE.
Arizona Lithium plans to bring initial production for Prairie online in the first half of 2025 before building production up to between 20,000 and 25,000 tpa of LCE in Phase Two, and ‘multiples of that’ in Phase Three.
Managing Director Paul Lloyd says the new PFS showcases the ‘world-class’ nature of the company’s Prairie project.
“This PFS will stand up to any evaluation by shareholders and industry participants, and I am very proud of the team’s confidence and professional integrity to put these realistic and robust numbers out into the public domain.
After we have delivered the first module, the company aims to sanction further modules at the same or better economics to the first module. We are now ready to begin drilling the production and disposal wells and ordering equipment for production starting in 2025.”
“We are now ready to begin drilling the production and disposal wells and ordering equipment for production starting in 2025”
Global engineering group Samuel Engineering acted as the lead consultant to Arizona for the Prairie PFS.
Alongside Prairie, Arizona’s other main focus is its Big Sandy Lithium Project near Phoenix in the US.
Arizona Lithium had $10.67 million cash and cash equivalents at hand as of 30 September, according to its latest quarterly report. The company raised $16.5 million through an oversubscribed share placement in December.
Write to Joshua Smith at Mining.com.au
Images: Arizona Lithium