NevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plantStrategic Energy tests two Canobie targets NevGold pushes beyond Limo Butte resourceHeritage drills six-metre gold zone at MelbaSalazar discovers ‘high-grade’ tungsten at Pijili ProjectAguia aligned with newly approved government-backed fertiliser incentiveUS Department of Energy injects $13.9 million into critical mineralsQueensland legislation backs critical minerals explorationDevEx follows Nabarlek-style clues at KPAlurion drills towards Amargosa Prefeasibility StudyMoonlight hits broad copper zones at Peak DownsLegal battle heats up for major iron ore miner FortescueLithium Universe recovers gallium and platinum from e-wasteRokeby reports maiden tailings resource at OmeoCritical Resources links up with CSIRO for battery technologyBarkly advances 10,000m drilling at flagship projectAntilles Gold signs binding deal for Cuban sanction reliefRenegade expands loan facility to $2 millionUS Army’s Janus Program puts spotlight on uranium supplyMithril extends Copalquin silver-gold corridor to 550mFelix Gold produces antimony metal from pilot plantStrategic Energy tests two Canobie targets

Anson granted conditional use permit at Utah plant

Anson Resources (ASX:ASN) has received a conditional use permit (CUP) from the Green River City Planning & Zoning Commission for drilling on the area of its proposed Utah Sample Demonstration Plant (USDP).

The CUP application for exploration permits was lodged in December 2023 for the USDP at the company’s Green River Lithium Project in the Paradox Basin in south-eastern Utah, US.

Anson says approval is an important step in its plans to develop the Green River Project in parallel with its lead project, the nearby Paradox Lithium Project.

The grant of the CUP follows the Green River City Council’s approval of the re-zoning of Anson’s privately owned ground at the Green River Project for exploration drilling and mineral processing.

The CUP will allow Anson to conduct exploration drilling adjacent to the proposed USDP. The aim will be utilising the brine from the drilled well directly into the lithium extraction process at the demonstration plant to replicate as closely as possible the operating conditions of the company’s proposed future full-scale production plant.

This will include the temperature of the brine and make-up of the brine, including the lithium grade.

Anson is of the view that this information will contribute to the further de-risking of the project by helping to provide greater certainty on the attributes of the Project’s lithium brines for potential offtake partners.

Anson started construction of the USDP in November 2023. Progress has been achieved in recent weeks with the construction of fencing surrounding the plant site, preparation of a drilling pad, along with connection of grid power and other utilities.

Equipment from the Anson’s Lithium Innovation Centre (LIC) has been replicated and will be installed in the USDP. With the CUP now in place, applications for the planned drilling program have been made to the Utah Division of Oil and Gas (UDOGM) and are progressing through the approval stages.

The CUP also allows for a planned Visitor Centre to progress at the Green River site. The company plans to use Visitor Centre and the USDP for meetings with potential offtake partners, OEMs, Cathode Active Materials producers, and potential funders of the planned full-scale production plant.

Write to Adam Orlando at Mining.com.au

Images: Anson
Add to Watch List:
Author Image
Written By Adam Orlando
Mining.com.au Editor-in-Chief Adam Orlando has more than 20 years’ experience in the media having held senior roles at various publications, including as Asia-Pacific Sector Head (Mining) at global newswire Acuris (formerly Mergermarket). Orlando has worked in newsrooms around the world including Hong Kong, Singapore, London, and Sydney.